BLD-Final | 2/26/2020 | 2/27/2020 | 2/26/2020 | P | PASS |
Jim Storey
|
|
|
Chad Phone #: ###-####
|
DOC - Permit Finaled | 2/26/2020 | 2/26/2020 | 2/26/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 8/15/2019 | 8/16/2019 | 8/16/2019 | A | PASS |
Jim Storey
|
|
|
Chad Phone #: ###-####
|
BLD-Framing/Rough-in | 8/14/2019 | 8/14/2019 | 8/14/2019 | P | PASS |
Dave Hannah
|
|
|
Chad Phone #: ###-####
|
BLD-Framing/Rough-in | 8/12/2019 | 8/13/2019 | 8/13/2019 | P | FAIL |
Tell Riley
|
|
|
reschedule to 8/13th pm Chad Phone #: ###-####//correction notice issued--2 pages//no plans or truss engineering onsite//
|
Routing - MECHANICAL | 8/9/2019 | | 8/9/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 8/5/2019 | 8/6/2019 | 8/6/2019 | A | PASS |
Jim Storey
|
|
|
Chad Phone #: ###-####
|
BLD-Foundation | 6/19/2019 | 6/19/2019 | 6/19/2019 | P | PASS |
Jim Storey
|
|
|
Brian Phone #: ###-####
|
BLD-Footing | 6/14/2019 | 6/17/2019 | 6/17/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 6/14/2019 | 6/17/2019 | 6/17/2019 | A | CANC |
Brandon Shaw
|
|
|
Ryan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/12/2019 | | DONE |
|
|
|
|
Telephone call | | | 3/21/2019 | | DONE |
|
|
|
called Ryan to let know permit is ready once we receive the letter for Brent Moore in P&Z. Brent really should approve before we issue-customer Ryan knows we need that and what the fees due are
|
OVERRIDE | | | 3/20/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 3/6/2019 | 3/6/2019 | 3/20/2019 | | DONE |
Jenny Nelson
|
|
|
03/19 sfd L1 Paper. 1st complete 3/12, wall bracing issues, show attic and crawl accesses.
|
Inspection Record Card- Bld | | | 3/20/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 3/20/2019 | | 3/20/2019 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 3/20/2019 | | DONE |
|
|
|
Make sure with Brent Moore has the letter from the irragation company allowing to build on that parcel
|
Routing - PLAN CHECK | 3/15/2019 | | 3/15/2019 | | PASS |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 3/15/2019 | | DONE |
Jenny Nelson
|
|
|
|
Plan resubmittals received | | | 3/14/2019 | | DONE |
|
|
|
8 copies of braced wall line length calculations, two copies of sheets A-2, A-3 and A-4. taken to Jenny
|
Routing - FIRE | 3/12/2019 | 3/12/2019 | 3/13/2019 | | PASS |
Lee G Meredith
|
|
|
03/19 Highland St. Residence
Sprinklers not required. LGM
|
1st review completed | | | 3/13/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 3/12/2019 | | 3/12/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 3/7/2019 | | 3/12/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - MECHANICAL | 3/7/2019 | | 3/11/2019 | | FAIL |
Troy James
|
|
|
|
Route to Impact Fee Review | 3/6/2019 | 3/9/2019 | 3/7/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 3/6/2019 | | 3/7/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 3/6/2019 | | 3/7/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/6/2019 | | DONE |
|
|
|
|
Intake Approval | | | 3/6/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/6/2019 | | DONE |
|
|
|
|
Application received | | 3/6/2019 | | | |
|
|
|
Applicant contacted 3/7/19 via email. Need approval from boise canal co.
|