BLD-Final | 12/16/2019 | 12/16/2019 | 12/16/2019 | A | PASS |
Jim Storey
|
|
|
|
DOC - Permit Finaled | 12/16/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 12/16/2019 | 12/16/2019 | 12/16/2019 | A | DONE |
Jim Storey
|
|
|
2.6
|
BLD-Framing/Rough-in | 10/25/2019 | 10/25/2019 | 10/25/2019 | P | PASS |
Jim Storey
|
|
|
ok to cover
|
BLD-Energy code compliance | 10/22/2019 | 10/23/2019 | 10/23/2019 | A | PASS |
Jim Storey
|
|
|
Inspection requested via web by Rob Ashworth
|
BLD-Framing/Rough-in | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Ashworth soffits ok.
|
BLD-Framing/Rough-in | 10/18/2019 | 10/21/2019 | 10/21/2019 | P | CANC |
Jim Storey
|
|
|
Jim, Can you call me when you arrive for inspection. Thank you Rob. Phone #: ###-#### >> Inspection requested via web by Rob Ashworth Inspection cancelled from web by: Rob Ashworth
|
BLD-Framing/Rough-in | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | FAIL |
Jim Storey
|
|
|
Inspection requested via web by Rob Ashworth front sopffits porch and garage covered w/o fire treated ply// no listing for hardboard sidding to be non combustable.
|
BLD-Wall Bracing | 10/9/2019 | 10/9/2019 | 10/9/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Rob Ashworth
|
BLD-Foundation | 9/20/2019 | 9/23/2019 | 9/23/2019 | P | PASS |
Jim Storey
|
|
|
Jerry Phone #: ###-####
|
BLD-Footing | 9/19/2019 | 9/20/2019 | 9/23/2019 | P | PASS |
Jim Storey
|
|
|
Jerry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/12/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/12/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 5/22/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 5/9/2019 | 5/9/2019 | 5/22/2019 | | DONE |
Rob Patrick
|
|
|
05/22 sfd L1 ePlan
|
Routing - PLAN CHECK | 5/9/2019 | | 5/22/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 5/22/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/22/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 5/22/2019 | | DONE |
|
|
|
met
|
Route to Impact Fee Review | 5/9/2019 | 5/12/2019 | 5/10/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 5/9/2019 | | 5/10/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 5/9/2019 | | 5/9/2019 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 5/9/2019 | | 5/9/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 5/9/2019 | | 5/9/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/9/2019 | | DONE |
|
|
|
|
Intake Approval | | | 5/9/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/9/2019 | | DONE |
|
|
|
|
Application received | | | 5/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on May 8 2019 3:54PM
|