BLD-Final | 1/28/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Jim Storey
|
|
|
Inspection requested via web by Rob Ashworth
|
DOC - Permit Finaled | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Blower Door Test Results | 1/29/2020 | 1/29/2020 | 1/29/2020 | P | DONE |
Jim Storey
|
|
|
Inspection requested via web by Rob Ashworth 4.5
|
BLD-Energy code compliance | 12/10/2019 | 12/10/2019 | 12/10/2019 | P | PASS |
Jim Storey
|
|
|
Inspection requested via web by Rob Ashworth
|
BLD-Wall cover | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Jim Storey
|
|
|
Drywall, in soffits and eaves. WUI conditions. Inspection requested via web by Rob Ashworth
|
BLD-Framing/Rough-in | 12/5/2019 | 12/6/2019 | 12/6/2019 | A | PASS |
Jim Storey
|
|
|
Inspection requested via web by Rob Ashworth
|
BLD-Wall Bracing | 11/22/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Jim Storey
|
|
|
Inspection requested via web by Rob Ashworth
|
BLD-Footing | 11/1/2019 | 11/4/2019 | 11/4/2019 | P | PASS |
Jim Storey
|
|
|
Pat Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/4/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/4/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/22/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/27/2019 | 6/27/2019 | 8/22/2019 | | PASS |
Josh Bogle
|
|
|
07/01 sfd L1 ePlan - 1st done
|
Routing - PLAN CHECK | 8/22/2019 | | 8/22/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 8/22/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 8/13/2019 | | 8/13/2019 | | FAIL |
Josh Bogle
|
|
|
no rating for soffit detail
|
Plan Reviewer's activity | | | 7/22/2019 | | DONE |
Josh Bogle
|
|
|
removed vent specifications per applicant's request
|
Routing - PLAN CHECK | 7/22/2019 | | 7/22/2019 | | FAIL |
Josh Bogle
|
|
|
attic venting not WUI approved
|
Plan Reviewer's activity | | | 7/3/2019 | | DONE |
Josh Bogle
|
|
|
accepted resubmittal - re-review shows problems with WUI roof venting - sitting on this review while Rob works thist out with CBH and the Fire Marshall
|
Plan assigned to (RDP) | 6/18/2019 | 6/18/2019 | 6/27/2019 | | DEFR |
Rob Patrick
|
|
|
07/01 sfd L1 ePlan
|
Routing - PLAN CHECK | 6/18/2019 | | 6/27/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Melissa
|
1st review completed | | | 6/27/2019 | | FAIL |
Josh Bogle
|
|
|
|
Route to Impact Fee Review | 6/18/2019 | 6/21/2019 | 6/19/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/18/2019 | | 6/19/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 6/18/2019 | | 6/19/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/18/2019 | | 6/18/2019 | | PASS |
Angela Hardy
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/18/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/18/2019 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2019 | | PASS |
|
|
|
|
Routing - PLANNING | 6/18/2019 | | 6/18/2019 | | PASS |
Sue Cummings
|
|
|
|
Application received | | | 6/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 17 2019 4:37PM
|