CHANGE STATUS TO (ISS) | | | 4/8/2020 | | DONE |
|
|
|
Waiting for MEC final to pass. Per Brandon S
|
BLD-Final | 4/6/2020 | 4/7/2020 | 4/7/2020 | A | PASS |
Brandon Shaw
|
|
|
REMOTELEY INSP- Mike Phone #: ###-####
|
DOC - Permit Finaled | 4/7/2020 | 4/7/2020 | 4/7/2020 | P | PASS |
Brandon Shaw
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/6/2020 | | DONE |
|
|
|
per brandon should not be closed
|
BLD-Conference | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | DONE |
Brandon Shaw
|
|
|
call for access- Michael Phone #: ###-####
|
DOC - Permit Finaled | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Energy code compliance | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | PASS |
Brandon Shaw
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/11/2020 | 2/12/2020 | 2/12/2020 | A | PASS |
Brandon Shaw
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 1/21/2020 | 1/22/2020 | 1/22/2020 | P | PART |
Brandon Shaw
|
|
|
Kitchen area only...
|
BLD-Conference | 12/18/2019 | 12/19/2019 | 12/19/2019 | P | DONE |
Brandon Shaw
|
|
|
Mike Phone #: ###-####
|
BLD-Wall Bracing | 11/15/2019 | 11/18/2019 | 11/18/2019 | A | PASS |
Brandon Shaw
|
|
|
shear // Dale Phone #: ###-####
|
BLD-Foundation | 10/25/2019 | 10/28/2019 | 10/28/2019 | A | DONE |
Dave Hannah
|
|
|
as early as possible // Jim Phone #: ###-####
|
BLD-Foundation | 10/24/2019 | 10/25/2019 | 10/25/2019 | P | DEFR |
Jim Storey
|
|
|
as early as possible // Jim Phone #: ###-####//out of time
|
PubWorks Subgrade Approval | 10/22/2019 | 10/22/2019 | 10/22/2019 | | DONE |
Melissa Jannusch
|
|
|
SONOTUBES *A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
PubWorks Subgrade Approval | 10/4/2019 | 10/4/2019 | 10/4/2019 | | DONE |
Melissa Jannusch
|
|
|
*FOOTINGS* DOES NOT INCLUDE SONOTUBES! A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 8/27/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/27/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/27/2019 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 8/26/2019 | 8/26/2019 | 8/26/2019 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 7/2/2019 | 7/2/2019 | 8/26/2019 | | PASS |
Josh Bogle
|
|
|
07/08 additon, paper - 1st done
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Routing - PLAN CHECK | 8/26/2019 | | 8/26/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 8/26/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 8/26/2019 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/23/2019 | | 8/23/2019 | | FAIL |
Josh Bogle
|
|
|
|
Plan resubmittals received | | | 8/22/2019 | | DONE |
|
|
|
3 brand new copies of plans. Engineering for deck, truss calcs for existing trusses
|
Routing - PLAN CHECK | 8/15/2019 | | 8/15/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 8/13/2019 | | 8/13/2019 | | PASS |
Nicolette Womack
|
|
|
Stairs within side yard setback are allowed as only 1' above grade.
|
Routing - PUBLIC WORKS | 7/2/2019 | | 8/7/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Grading-Hillside | 8/6/2019 | | 8/6/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Plan resubmittals received | | | 7/18/2019 | | DONE |
|
|
|
3 large plan on drainage, copies of planning and development approval letters, 2 copies of Geotechnical Inv- given to Plan Reviewer- Josh
|
1st review completed | | | 7/18/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/17/2019 | | 7/18/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Mike
|
Routing - Erosion and Sediment | 7/15/2019 | | 7/17/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified stormwater team. Site preparation inspection is required.
|
Routing - PLANNING | | | 7/15/2019 | | FAIL |
Nicolette Womack
|
|
|
Need Fullsize grading and drainage plan per MMJ.
|
Routing PW Grading-Hillside | 7/5/2019 | | 7/8/2019 | | FAIL |
Melissa Jannusch
|
|
|
See e-mail to applicant 7-8-2019
|
Routing - Addressing | 7/3/2019 | | 7/3/2019 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 7/2/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/2/2019 | | DONE |
|
|
|
no fees paid at intake
|
Application received | | 6/25/2019 | | | |
|
|
|
|