BLD-Final | 3/23/2020 | 3/23/2020 | 3/23/2020 | P | PASS |
Mike Jordan
|
|
|
Ramon Phone #: ###-####
|
DOC - Permit Finaled | 3/23/2020 | 3/23/2020 | 3/23/2020 | P | PASS |
Mike Jordan
|
|
|
Fire dept. issues resolved. All other building issues were resolved.
|
BLD-Final | 3/12/2020 | 3/13/2020 | 3/13/2020 | A | NR |
Mike Jordan
|
|
|
Derek Phone #: ###-####. Still needs resolve fire dept. issues and building issues.
|
BLD-Final | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | NR |
Tony Young
|
|
|
call for access 30 mins- Anothony Phone #: ###-####// needs fire dept approval,, address posted,, blower door test verification number
|
Telephone call | | | 2/6/2020 | | DONE |
|
|
|
Ron Johnson requested I call Mr. Sanchez to discuss fire code requirements for this property. I discussed the code requirements with Mr. Sanchez and informed him that due to access and hydrant distances and the fact that his driveway is not paved, he would have to install a fire sprinkler system. He indicated that he did not want to. I informed him that if the access distances can be reduced to within maximums allowed and the driveway meets minimal requirements that he would not have to install sprinklers. I spoke with Ron Johnson on 2-6-20 and he confrimed my comments. Ron also indicated that a report from a qualified engineering firm would be required for the driveway meeting the minimal weight requirements. I emailed Mr. Sanchez this information.
|
BLD-Energy code compliance | 12/3/2019 | 12/5/2019 | 12/5/2019 | A | PASS |
Tony Young
|
|
|
rick Phone #: ###-####
|
BLD-Framing/Rough-in | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | PASS |
Tony Young
|
|
|
Rick Phone #: ###-####
|
BLD-Framing/Rough-in | 11/27/2019 | 12/2/2019 | 12/2/2019 | A | PART |
Tony Young
|
|
|
Rick Phone #: ###-####,, frame ok,, just needs mech pass
|
Routing - MECHANICAL | 11/22/2019 | | 11/22/2019 | | PASS |
Troy James
|
|
|
New manual j report
|
BLD-Wall Bracing | 11/12/2019 | 11/13/2019 | 11/13/2019 | P | PASS |
Tony Young
|
|
|
Rick Phone #: ###-####
|
BLD-Wall Bracing | 11/8/2019 | 11/12/2019 | 11/12/2019 | A | NR |
Tony Young
|
|
|
Rick Phone #: ###-####
|
BLD-Foundation | 10/8/2019 | 10/10/2019 | 10/10/2019 | A | PASS |
Tony Young
|
|
|
pour at 12 // dave Phone #: ###-####
|
BLD-Foundation | 10/7/2019 | 10/8/2019 | 10/8/2019 | A | PASS |
Tony Young
|
|
|
pour at 11 // dave Phone #: ###-####// footings ok,, reviewed compaction test results,, ok
|
Inspection Record Card- Bld | | | 9/23/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/14/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/8/2019 | | |
|
|
|
|
Telephone call | | | 8/8/2019 | | DONE |
|
|
|
Left voicemail for Victoria to inform her the permit is ready, we need an RP and what fees are due.
MET RP
|
Inspection Record Card- Bld | | | 8/8/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/8/2019 | | DONE |
|
|
|
need RP
|
Plan resubmittals received | | | 8/7/2019 | | DONE |
|
|
|
Two copies of site plan taken to jenny
|
Routing - PLANNING | 8/7/2019 | | 8/7/2019 | | PASS |
Sue Cummings
|
|
|
New site plan receive 8/7/19
|
Case Summary (BLD) | | | 8/7/2019 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2019 | | DONE |
Jenny Nelson
|
|
|
|
Plan assigned to (J_N) | 7/12/2019 | | 8/7/2019 | | DONE |
Jenny Nelson
|
|
|
07/25 sfd L1 Paper. 1st complete 7/22, failed planning
|
Routing - PLAN CHECK | 7/17/2019 | | 7/22/2019 | | PASS |
Jenny Nelson
|
|
|
|
1st review completed | | | 7/22/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 7/15/2019 | | 7/17/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 7/12/2019 | 7/15/2019 | 7/15/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 7/12/2019 | | 7/15/2019 | | FAIL |
Sue Cummings
|
|
|
Inadiquate site plan. It needs to be drawn to scale and include the following information: property lines adjacent streets decks covered patios driveways and sidewalks.
|
Routing - Addressing | 7/12/2019 | | 7/12/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/12/2019 | | 7/12/2019 | | PASS |
Angela Hardy
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/12/2019 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/12/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/10/2019 | | FAIL |
Judith Amador
|
|
|
|
Meeting | | | 7/10/2019 | | |
|
|
|
GC was not added to case because parcel owner wants to be the permit holder to begin the process, please verify with owner if they would like to continue as the acting GC.
|
Application received | | 7/10/2019 | | | |
|
|
|
|