BLD-Final | 12/30/2019 | 12/30/2019 | 12/30/2019 | A | PASS |
Brandon Shaw
|
|
|
|
DOC - Permit Finaled | 12/30/2019 | 12/30/2019 | 12/30/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 12/26/2019 | 12/27/2019 | 12/27/2019 | A | NR |
Brandon Shaw
|
|
|
Smoke/carbon alarms to be up dated and interconnected...
|
BLD-Energy code compliance | 10/21/2019 | 10/22/2019 | 10/22/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Jake Stone
|
BLD-Framing/Rough-in | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Brandon Shaw
|
|
|
No ADU, stove top and hood is OK... NO OVEN ALLOWED...
|
BLD-Framing/Rough-in | 10/17/2019 | 10/18/2019 | 10/18/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Jake Stone
|
Fees Due Hold | 10/18/2019 | | 10/18/2019 | | DONE |
|
|
|
|
Routing - MECHANICAL | 10/16/2019 | | 10/17/2019 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
Plan Modification Accepted | | | 10/15/2019 | | DONE |
|
|
|
Eplan work flow opened for new Manual J
|
BLD-Wall Bracing | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PEND |
Brandon Shaw
|
|
|
OK to cover exterior... No roof sheeting at time of inspection...
|
BLD-Foundation | 9/13/2019 | 9/16/2019 | 9/16/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru
|
BLD-Footing | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 9/11/2019 | 9/12/2019 | 9/11/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru Inspection cancelled via mobile web on Wednesday, September 11, 2019.
|
Inspection Record Card- Bld | | | 8/20/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/19/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 8/16/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 8/16/2019 | 8/16/2019 | 8/16/2019 | P | PASS |
Josh Bogle
|
|
|
|
Issue PAID IN FULL permit | | | 8/16/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/16/2019 | | DONE |
|
|
|
met: NEED RP
|
Plan assigned to (JAB) Josh | 7/22/2019 | 7/22/2019 | 8/15/2019 | | PASS |
Josh Bogle
|
|
|
07/26 addition, ePlan - 1st done
|
Routing - PLAN CHECK | 8/15/2019 | | 8/15/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Routing - PLANNING | 8/12/2019 | | 8/12/2019 | | PASS |
Sue Cummings
|
|
|
Removed the proposed kitchen
|
Routing - PLAN CHECK | 8/12/2019 | | 8/12/2019 | | FAIL |
Josh Bogle
|
|
|
see Changemarks in ePlan
|
Routing - PLAN CHECK | 7/29/2019 | | 8/9/2019 | | FAIL |
Josh Bogle
|
|
|
no review pending Planning approval
|
Routing - PLANNING | 7/29/2019 | | 7/30/2019 | | FAIL |
Sue Cummings
|
|
|
Please provide a floor plan of entire house.
|
Routing - MECHANICAL | 7/29/2019 | | 7/29/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to western htg
|
Routing - MECHANICAL | 7/29/2019 | | 7/29/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 7/22/2019 | | 7/29/2019 | | FAIL |
Josh Bogle
|
|
|
no review pending Planning approval - route to Mech?
|
1st review completed | | | 7/29/2019 | | FAIL |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 7/29/2019 | | DONE |
Josh Bogle
|
|
|
accepted and routed resubmittal
|
Routing - PLANNING | 7/22/2019 | | 7/22/2019 | | FAIL |
Sue Cummings
|
|
|
Please show on the floor plan how the old kitchen will be used. There can only be one kitchen.
|
Plans ACCEPTED BY PLAN TECH | | | 7/22/2019 | | DONE |
|
|
|
|
Intake Approval | | | 7/22/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/22/2019 | | DONE |
|
|
|
|
Application received | | | 7/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2019 3:45PM
|
Intake Approval | | | 7/17/2019 | | FAIL |
|
|
|
Please provide a full floor plan of before and after
|
Intake Approval | | | 7/17/2019 | | FAIL |
|
|
|
still missing full floor plan
|