BLD-Final | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Brandon Shaw
|
|
|
Finalize deck structure. Electrician is finalled. Thanks Phone #: ###-#### Inspection requested via web by Dustin Collins
|
DOC - Permit Finaled | 10/18/2019 | 10/18/2019 | 10/18/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 9/5/2019 | 9/6/2019 | 9/6/2019 | P | PASS |
Tony Young
|
|
|
Jace Phone #: ###-####
|
BLD-Energy code compliance | 8/22/2019 | 8/26/2019 | 8/26/2019 | A | PASS |
Tony Young
|
|
|
Please call 15 minutes before inspection so that our project manager can be on site. Gate code #1937 Phone #: ###-#### Inspection requested via web by Dustin Collins// insulation under deck area over living space
|
BLD-Foundation | 8/6/2019 | 8/7/2019 | 8/7/2019 | P | PART |
Tony Young
|
|
|
We will be formed and ready for our sono tubes and stem wall inspection in the afternoon. Gate code #1937. Thanks Phone #: ###-#### Inspection requested via web by Dustin Collins// work in progress
|
BLD-Foundation | 8/6/2019 | 8/7/2019 | 8/6/2019 | A | CANC |
Tony Young
|
|
|
Stem wall inspection prior to pouring walls. These have #4 bar and are formed up and ready. Thanks, Dustin Gate Code #1937 Phone #: ###-#### >> Inspection requested via web by Dustin Collins Inspection cancelled from web by: Dustin Collins
|
BLD-Footing | 8/4/2019 | 8/5/2019 | 8/5/2019 | P | PART |
Tony Young
|
|
|
Please call prior to arrival so we can be present. There is a gate code #1937 to enter the community. Thanks, Dustin Phone #: ###-#### Inspection requested via web by Dustin Collins// work in progress
|
Routing Walk-In (BLD) | 8/1/2019 | 8/1/2019 | 8/1/2019 | A | DONE |
Josh Bogle
|
|
|
Submitting additional paper work that was requested
|
Routing - PLAN CHECK | 8/1/2019 | | 8/1/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 8/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 8/1/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy yes
|
Permit Ready to Issue | | | 8/1/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/1/2019 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | FAIL |
Josh Bogle
|
|
|
still talking
|
Routing Walk-In (BLD) | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/31/2019 | | 7/31/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Dustin
|
Plan resubmittals received | | | 7/30/2019 | | DONE |
|
|
|
Adjust width of shear wall, added insulation details, provided engineering
|
Routing Walk-In (Zoning) | 7/26/2019 | 7/26/2019 | 7/26/2019 | A | DONE |
Sue Cummings
|
|
|
|
Routing Walk-In (BLD) | 7/26/2019 | 7/26/2019 | 7/26/2019 | A | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/26/2019 | | 7/26/2019 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 7/26/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 7/26/2019 | | | |
|
|
|
|