Information based on query as of Tuesday, May 14, 2024.
Permit Information
Permit NumberBLD19-03567
StatusIssued
Name INDIE DWELL INC
Site Address 7869 W SETTLERS AVE
Project NameSETTLERS
Customer NumberSEE DESC FOR INSIGNA #S
ePlanReviewNo
Description
**PLAN MODIFICATION - Changing foundation from individual footings to continuous footings. JJN 10/09/19** STATE OF IDAHO DIVISION OF BUILDING SAFETY APPROVED PLAN; PA#: MOD1906-00040. Permit for the construction of a new 960 sq. ft., one story single family dwelling with 4 bedrooms, 2 bathrooms, approximately 0 sq. ft. of covered patio/porch and a 210 sq. ft. slab per the approved plans and any notations. Driveway is existing. Prescriptive Energy Compliance. R-1C zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
CHANGE STATUS TO (ISS)  4/29/2020 DONE
OVERRIDE  4/21/2020  
Routing - MECHANICAL4/21/2020 4/21/2020 PASS
DetailsTroy James
ACCA report submitted
Permit Ready to Issue  4/21/2020 DONE
DO NOT ISSUE- plan mod approved see email in documents
BLD-Foundation10/18/201910/21/201910/21/2019APASS
DetailsTell Riley
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru//need to add weld plates//
BLD-Foundation10/17/201910/18/201910/18/2019PCANC
DetailsTell Riley
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo aggregate constru Inspection cancelled via mobile web on Friday, October 18, 2019.
BLD-Footing10/16/201910/17/201910/17/2019APASS
DetailsTell Riley
Phone #: 2089495359 >> Inspection requested via mobile web by Ricardo
Inspection Record Card- Bld  10/11/2019 DONE
CHANGE STATUS TO (ISS)  10/11/2019 DONE
OVERRIDE  10/9/2019  
Plan assigned to (J_N)10/8/201910/8/201910/9/2019 DONE
Details
Plan assigned to (JAB) Josh10/8/201910/8/201910/9/2019 CANC
DetailsJenny Nelson
Routing - PLAN CHECK10/9/2019 10/9/2019 PASS
DetailsJenny Nelson
1 hour plan mod fee
Case Summary (BLD)  10/9/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  10/9/2019 DONE
plan mod approved.
Telephone call  10/9/2019 DONE
Mail box is full, could not leave voicemail for plan mod
Plan Modification Accepted  10/8/2019 DONE
Changing footings
OVERRIDE  9/27/2019  
Plan assigned to (J_N)9/11/20199/11/20199/27/2019 DONE
DetailsJenny Nelson
09/26 sfd L1 ePlan
Routing - PLAN CHECK9/18/2019 9/27/2019 PASS
DetailsJosh Bogle
Issue PAID IN FULL permit  9/27/2019 DONE
1st review completed  9/27/2019 DONE
DetailsJenny Nelson
Inspection Record Card- Bld  9/27/2019 DONE
DetailsJenny Nelson
Case Summary (BLD)  9/27/2019 DONE
DetailsJenny Nelson
PLANS/APPL TAKEN TO FRONT DESK  9/27/2019 DONE
DetailsJenny Nelson
Permit Ready to Issue  9/27/2019 DONE
Routing - PLANNING9/26/2019 9/26/2019 PASS
DetailsSue Cummings
Received floor plan 9/26/19. See minor redline
Plan resubmittals received  9/24/2019  
DetailsJenny Nelson
plan resubmittals mysteriously appeared on my desk with a note, "To Jenny N".
Routing - PLANNING9/16/2019 9/16/2019 FAIL
DetailsSue Cummings
Redlines on site plan. Needs a floor plan.
Routing - PUBLIC WORKS9/11/2019 9/16/2019 PASS
DetailsMorgan Webb
CONTACT WEST BOISE SEWER DISTRICT ###-####
Routing - Addressing9/11/2019 9/16/2019 PASS
DetailsDoug Chausow
Route to Impact Fee Review9/11/20199/14/20199/12/2019 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Plans ACCEPTED BY PLAN TECH  9/11/2019 DONE
Recd Pcfee & Taken To Pln CK  9/11/2019 DONE
no intake fee taken-
Intake Approval  9/11/2019 PASS
Application received 9/11/2019