PubWorks Occupancy Approval | 8/13/2020 | 8/13/2020 | 8/13/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer/landscape architect indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
Override - Parcel Holds | | | 8/13/2020 | | |
|
|
|
|
BLD-Foundation | 12/6/2019 | 12/9/2019 | 12/9/2019 | A | PART |
Tony Young
|
|
|
Rebar- Josh Phone #: ###-####,, retaining wall
|
BLD-Footing | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PART |
Tony Young
|
|
|
Rebar- Josh Phone #: ###-####,,footings poured,, work in progress on wall rebar
|
BLD-Footing | 11/22/2019 | 11/25/2019 | 11/25/2019 | A | PART |
Tony Young
|
|
|
CAL Phone #: ###-####,, ok to pour footing
|
BLD-Footing | 11/22/2019 | 11/22/2019 | 11/22/2019 | P | PART |
Tony Young
|
|
|
CAL Phone #: ###-####,, work in progress on footing,, 90% done
|
PubWorks Subgrade Approval | 11/22/2019 | 11/22/2019 | 11/22/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 11/13/2019 | | DONE |
|
|
|
|
Telephone call | | | 11/5/2019 | | DONE |
|
|
|
Emailed the parcel owner to let him know that all fees must be paid (and included the fees due). Also let him know that they would need an RP.
|
OVERRIDE | | | 11/4/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 11/4/2019 | 11/4/2019 | 11/4/2019 | P | DONE |
Josh Bogle
|
|
|
conference with Josh on what additional plans or document needed
|
Plan assigned to (JAB) Josh | 10/23/2019 | 10/23/2019 | 11/4/2019 | | PASS |
Josh Bogle
|
|
|
10/29 retaining wall, ePlan - 1st done
|
Routing - PLAN CHECK | 11/4/2019 | | 11/4/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/4/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy no
|
Permit Ready to Issue | | | 11/4/2019 | | DONE |
|
|
|
MET
Need RP
|
1st review completed | | | 11/1/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing PW Grading-Hillside | 10/23/2019 | | 11/1/2019 | | PASS |
Melissa Jannusch
|
|
|
RETAINING WALL ONLY
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PLANNING | 10/23/2019 | | 10/29/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - PLAN CHECK | 10/23/2019 | | 10/28/2019 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
Plan Reviewer's activity | | | 10/28/2019 | | DONE |
Josh Bogle
|
|
|
noticed there was no Hillside task in ePlan, added it
|
Routing - PUBLIC WORKS | 10/23/2019 | | 10/23/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 10/23/2019 | | 10/23/2019 | | PASS |
Andy J. Long
|
|
|
ESC site plan and narrative approved. RP not yet listed. Site preparation inspection required prior to earth work.
|
Plans ACCEPTED BY PLAN TECH | | | 10/23/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/23/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/23/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/21/2019 | | FAIL |
|
|
|
Approved under CFH17-00063. Please move the documents to the documents folder and have the drawings in the drawings folder.(we can delete the files for you) Melissa Jannusch ###-####
|
Application received | | | 9/20/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 20 2019 11:23AM
|