BLD-Final | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Mike Jordan
|
|
|
Preston Phone #: ###-####
|
DOC - Permit Finaled | 1/9/2020 | 1/9/2020 | 1/9/2020 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Final | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | FAIL |
Mike Jordan
|
|
|
Jay Phone #: ###-####. Needs to provide the lateral bracing on the A2 truss as shown on the engineering.
|
BLD-Framing/Rough-in | 12/23/2019 | 12/23/2019 | 12/23/2019 | P | PART |
Mike Jordan
|
|
|
Preston - east side gate is open Phone #: ###-####. Ok to cover. Needs to supply the truss engineering on final.
|
BLD-Foundation | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
Mike Jordan
|
|
|
pour at 11 // preston Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/19/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/19/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 11/4/2019 | 11/4/2019 | 11/15/2019 | | PASS |
Josh Bogle
|
|
|
11/08 patio cover, ePlan - 1st done
|
Routing - PLAN CHECK | 11/15/2019 | | 11/15/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/15/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 11/15/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 11/4/2019 | | 11/4/2019 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan
|
Routing - PLANNING | 11/4/2019 | | 11/4/2019 | | PASS |
Ethan Mansfield
|
|
|
|
1st review completed | | | 11/4/2019 | | FAIL |
Josh Bogle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/4/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/4/2019 | | DONE |
|
|
|
no intake fee taken -406 app
|
Intake Approval | | | 11/4/2019 | | PASS |
|
|
|
|
Application received | | | 10/16/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 16 2019 11:54AM
|
Intake Approval | | | 10/16/2019 | | FAIL |
|
|
|
Requires engineering. Josh called applicant
|