BLD-Energy code compliance | 6/28/2020 | 6/29/2020 | 6/29/2020 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2084845395 >> Inspection requested via mobile web by Ben covert
|
BLD-Energy code compliance | 6/25/2020 | 6/26/2020 | 6/26/2020 | A | FAIL |
Mike Jordan
|
|
|
Phone #: 20848455 >> Inspection requested via mobile web by Ben covert. Tall walls(living room) were batt insulation has used shall be encapsulated on all six sides. Correction notice posted.
|
BLD-Framing/Rough-in | 6/13/2020 | 6/15/2020 | 6/15/2020 | A | PASS |
Brandon Shaw
|
|
|
OK toinsulate...
|
BLD-Energy code compliance | 6/13/2020 | 6/15/2020 | 6/15/2020 | A | CANC |
Brandon Shaw
|
|
|
Phone #: 2084845395 >> Inspection requested via mobile web by Ben covert
|
BLD-Wall Bracing | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Brandon Shaw
|
|
|
Ben *screened** Phone #: ###-####
|
BLD-Footing | 3/19/2020 | 3/19/2020 | 3/19/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron int ftgs in slab
|
Elevation Cert Rec'd-Midconst | | | 3/11/2020 | | DONE |
|
|
|
Recieved EC #2
|
BLD-Foundation | 3/2/2020 | 3/2/2020 | 3/2/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
OVERRIDE | | | 2/13/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 1/28/2020 | 1/28/2020 | 2/13/2020 | | DONE |
Jenny Nelson
|
|
|
02/14 sfd L1 ePlan. 1st complete, floodplain corrections
|
Issue PAID IN FULL permit | | | 2/13/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2020 | | DONE |
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 2/13/2020 | | DONE |
|
|
|
|
Routing PW Flood Plain | 2/13/2020 | | 2/13/2020 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor -Boise City Public Works ###-####
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 2/13/2020 | | DONE |
|
|
|
MET
|
1st review completed | | | 2/11/2020 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 1/28/2020 | | 2/11/2020 | | PASS |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 1/28/2020 | | 1/31/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 1/28/2020 | | 1/30/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Flood Plain | 1/29/2020 | | 1/30/2020 | | FAIL |
Jason C. Taylor
|
|
|
Elevation Certificate elevations need to be placed on site plan, foundation plan, and cross section plans. Jason Taylor ###-####.
|
Route to Impact Fee Review | 1/28/2020 | 1/31/2020 | 1/29/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PUBLIC WORKS | 1/28/2020 | | 1/29/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - MECHANICAL | 1/28/2020 | | 1/29/2020 | | PASS |
Troy James
|
|
|
|
Application received | | | 1/28/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 28 2020 11:27AM
|
Plans ACCEPTED BY PLAN TECH | | | 1/28/2020 | | DONE |
|
|
|
|
Intake Approval | | | 1/28/2020 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/28/2020 | | DONE |
|
|
|
|