BLD-Energy code compliance | 7/20/2020 | 7/20/2020 | 7/20/2020 | P | PASS |
Brandon Shaw
|
|
|
SCREENED // Clarence Phone #: ###-####
|
BLD-Framing/Rough-in | 7/6/2020 | 7/6/2020 | 7/6/2020 | P | PASS |
Tony Young
|
|
|
Screened // Clarence Phone #: ###-####// ok to insulate
|
BLD-Wall Bracing | 6/3/2020 | 6/3/2020 | 6/3/2020 | P | PASS |
Tony Young
|
|
|
screened // Clarence Phone #: ###-####
|
BLD-Wall Bracing | 5/28/2020 | 5/29/2020 | 5/29/2020 | A | FAIL |
Mike Jordan
|
|
|
screened - Clarence Phone #: ###-####. Provide portal frame construction at garage door opening as shown on approved plans. Remove tyvek for wall bracing inspection. Correction notice posted.
|
BLD-Wall Bracing | 5/14/2020 | 5/15/2020 | 5/15/2020 | A | FAIL |
Tell Riley
|
|
|
Clarence *screened* Phone #: ###-####//need city approved plans onsite for inspections//
|
BLD-Foundation | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | PASS |
Dave Hannah
|
|
|
Screened- stem wall- Mario Phone #: ###-####
|
BLD-Footing | 4/24/2020 | 4/27/2020 | 4/27/2020 | A | PASS |
Dave Hannah
|
|
|
Mario Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/27/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 2/24/2020 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 2/18/2020 | 2/18/2020 | 2/24/2020 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 2/24/2020 | | 2/24/2020 | | PASS |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/24/2020 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 2/24/2020 | | DONE |
|
|
|
NEED- RP
|
1st review completed | | | 2/20/2020 | | FAIL |
Debbie Sanine
|
|
|
|
Route to Impact Fee Review | 2/18/2020 | 2/21/2020 | 2/19/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 2/18/2020 | | 2/19/2020 | | PASS |
Ted Vanegas
|
|
|
|
Routing - Addressing | 2/18/2020 | | 2/19/2020 | | PASS |
Laura Hunter
|
|
|
ADU Address will be 1507 W Irene St
|
Routing - PUBLIC WORKS | 2/18/2020 | | 2/18/2020 | | PASS |
Morgan Webb
|
|
|
|
Routing - MECHANICAL | 2/18/2020 | | 2/18/2020 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 2/18/2020 | | 2/18/2020 | | DONE |
Sue Cummings
|
|
|
Sent to Ted V.
|
Intake Approval | | | 2/18/2020 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/18/2020 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/18/2020 | | DONE |
|
|
|
|
Intake Approval | | | 2/3/2020 | | FAIL |
|
|
|
1st Prescreen-
1. please provide a Manuel J
2. need full building section
|
Application received | | | 1/31/2020 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 31 2020 4:41PM
|
Routing - PLAN CHECK | 2/18/2020 | | | | FAIL |
Debbie Sanine
|
|
|
|