Information based on query as of Sunday, June 2, 2024.
Permit Information
Permit NumberBLD20-00578
StatusIssued
Name SI CONSTRUCTION LLC
Site Address 6318 W TIERRA LN
Project NameLOT 7- UNIT G
Customer Number20-00560, 20-00576 TO 00584
ePlanReview 
Description
**PASSES USING UA TRADE-OFF**(TEN BUILDING PERMIT FILED UNDER BLD20-00560)Permit for the construction of a new 1602 sq. ft., 2 story (first story 986 sq. ft., second story 616 sq. ft.) Townhouse with 3 bedrooms, 2.5 bathrooms, approximately 197 sq. ft. of covered patio/porch and a 454 sq. ft. attached garage per the approved plans and any notations. R-2D zoning and setbacks per planning. D_S
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Wall Bracing7/27/20207/28/20207/28/2020APASS
DetailsMike Jordan
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells
BLD-Other7/6/20207/7/20207/7/2020APASS
DetailsMike Jordan
Phone #: 2088703262 >> Inspection requested via mobile web by Lucas Eells. .5/8 type x rock for exterior firewalls ok to cover with OSB, 1st floor only.
BLD-Foundation5/15/20205/18/20205/18/2020APASS
DetailsMike Jordan
pouring around 11 am - screened // Pat Phone #: ###-####
BLD-Footing5/11/20205/12/20205/12/2020APART
DetailsMike Jordan
Pat *screened* Phone #: ###-####
Routing - MECHANICAL5/7/2020 5/8/2020 PASS
DetailsTroy James
Plan Modification Accepted  5/7/2020 DONE
Brandon requested the workflow to be opened for new Manual J's.
Issue PAID IN FULL permit  4/8/2020 DONE
Inspection Record Card- Bld  4/8/2020 DONE
OVERRIDE  3/13/2020  
Plan assigned to (D_S) Debbie2/25/20202/25/20203/13/2020 DONE
DetailsDebbie Sanine
Routing - PLAN CHECK3/13/2020 3/13/2020 PASS
DetailsDebbie Sanine
PLANS/APPL TAKEN TO FRONT DESK  3/13/2020 DONE
DetailsDebbie Sanine
Permit Ready to Issue  3/13/2020 DONE
ISSUE WITH 20-00560, 20-00576 TO 00584
Routing - PLAN CHECK2/21/2020 3/6/2020 FAIL
DetailsDebbie Sanine
1st review completed  3/5/2020 FAIL
DetailsDebbie Sanine
Routing - Design Review2/26/2020 2/26/2020 PASS
DetailsJosh Wilson
Plan assigned to (J_N)2/21/20202/21/20202/25/2020 DEFR
DetailsJenny Nelson
03/11 townhouse L2 ePlan
Routing - PUBLIC WORKS2/21/2020 2/25/2020 PASS
DetailsMorgan Webb
Route to Impact Fee Review2/21/20202/24/20202/24/2020 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL2/21/2020 2/24/2020 PASS
DetailsTroy James
Routing - Addressing2/21/2020 2/24/2020 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  2/21/2020 DONE
Intake Approval  2/21/2020 PASS
Recd Pcfee & Taken To Pln CK  2/21/2020 DONE
Application received 2/20/2020