Final | 11/14/2018 | 11/14/2018 | 11/14/2018 | P | PASS |
Eric Story
|
|
|
Last 6 units. Final final :) Phone #: ###-#### Inspection requested via web by Kevin Burke Final ok ,card signed
|
Final | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PART |
Eric Story
|
|
|
3rd set of 6 on west building Phone #: ###-#### Inspection requested via web by Kevin Burke 105,106,205,206,305,306 units ok to occupy
|
Final | 10/29/2018 | 10/30/2018 | 10/30/2018 | A | PART |
Eric Story
|
|
|
103,104,203,204,303,304 units ok to occupy EC will verify all ranges and dryers on install of pigtails and will assume responsibility of install
|
Change Status to I | | | 10/29/2018 | | DONE |
|
|
|
per inspector-was finaled by mistake
|
Final | 10/23/2018 | 10/23/2018 | 10/23/2018 | P | PASS |
Eric Story
|
|
|
First 6 units on north end + ranges. Phone #: ###-#### Inspection requested via web by Kevin Burke All ranges checked out fine as well as the units 101,102,201,202,301,302
|
Final | 10/21/2018 | 10/22/2018 | 10/22/2018 | A | FAIL |
Eric Story
|
|
|
1st (6) units on north end. Phone #: ###-#### Inspection requested via web by Kevin Burke Cord end installed on ranges were done by others and needs verification of install is correct
|
Final | 10/21/2018 | 10/22/2018 | 10/22/2018 | A | CANC |
Eric Story
|
|
|
1st (6) units on north end. Phone #: ###-#### Inspection requested via web by Kevin Burke
|
Final | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Eric Story
|
|
|
Last six units final. Building final. Phone #: ###-#### Inspection requested via web by Kevin Burke Final for remaining 6 units ok
|
Change Status to I | | | 10/5/2018 | | DONE |
|
|
|
per Eric was finaled by mistake
|
Permanent Service | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Eric Story
|
|
|
South 6 units for rough, and service Phone #: ###-#### Inspection requested via web by Kevin Burke p/s u/g n ok 13 meters needed
|
Electrical Rough-In | 9/27/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Eric Story
|
|
|
South 6 units for rough Phone #: ###-#### Inspection requested via web by Kevin Burke Units 107,108,207,208,307,308 ok to cover
|
Electrical Rough-In | 9/9/2018 | 9/10/2018 | 9/10/2018 | A | PASS |
James Ady
|
|
|
3rd set if 6 units on west building Phone #: ###-#### Inspection requested via web by Kevin Burke 3rd set of 6 going N to S in West unit. OK to cover
|
Electrical Rough-In | 8/23/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Eric Story
|
|
|
2nd 6 units on south side of building. Phone #: ###-#### Inspection requested via web by Kevin Burke 2nd phase of 6 units from the North ok to cover
|
Rough-In Permanent Service | 8/13/2018 | 8/14/2018 | 8/14/2018 | A | PASS |
Eric Story
|
|
|
First 6 units and service. Phone #: ###-#### Inspection requested via web by Kevin Burke First Northern 6 units ok to cover p/s u/g n ok
|
Electrical Rough-In | 5/30/2018 | 5/31/2018 | 5/31/2018 | A | PASS |
Eric Story
|
|
|
Soffits in stairwell, columns Phone #: ###-#### Inspection requested via web by Kevin Burke Soffits abnd stairs only ok to cover
|
Issue PAID IN FULL permit | | | 5/30/2018 | | DONE |
|
|
|
Payment received via Govolutions
|
Application received | | | 5/30/2018 | | DONE |
|
|
|
This permit was created on the web by Kevin Burke
|
First Notice | 11/14/2018 | 11/14/2018 | | | |
Eric Story
|
|
|
|
First Notice | 10/5/2018 | 10/5/2018 | | | |
Eric Story
|
|
|
|