INSP-Final Inspection | 10/22/2008 | 10/22/2008 | 10/23/2008 | P | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Final Inspection | 10/22/2008 | 10/22/2008 | 10/22/2008 | A | PASS |
|
|
|
This permit is finaled per Forrest France.
|
INSP-Final Inspection | 2/25/2008 | 2/25/2008 | 2/25/2008 | P | DEFR |
Forrest France
|
|
|
Need plans and permit documents on site.
|
INSP-Sprinkler Rough-in/Hydro | 6/7/2007 | 6/7/2007 | 6/8/2007 | P | PART |
Forrest France
|
|
|
UG hydrostatic test of the fire supply line to the east building passed.
|
INSP-Sprinkler Rough-in | 5/16/2007 | 5/17/2007 | 5/17/2007 | A | PASS |
Troy Cobbley
|
|
|
underground cover inspection passed
|
INSP-Sprinkler Rough-in/Hydro | 2/20/2007 | 2/21/2007 | 2/21/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed. Contractor had to pump system back up to over 200lbs as I waited to begin test.
|
INSP-Sprinkler Rough-in/Hydro | 2/19/2007 | 2/20/2007 | 2/21/2007 | A | CANC |
Troy Cobbley
|
|
|
There is no time to perform inspection
|
INSP-Sprinkler Rough-in/Hydro | 2/1/2007 | 2/2/2007 | 2/2/2007 | A | PART |
Forrest France
|
|
|
Hydrostatic test for the OH FDC piping passed.
|
INSP-Sprinkler Rough-in/Hydro | 1/31/2007 | 2/1/2007 | 2/1/2007 | A | NR |
Forrest France
|
|
|
Per phone call from the subcontractor, system is not ready for hydro at this time, to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2007 | 1/31/2007 | 1/31/2007 | P | FAIL |
Forrest France
|
|
|
UG fire supply line hydrostatic test failed due to excessive pressure loss.
|
INSP-Sprinkler Rough-in/Hydro | 1/30/2007 | 1/30/2007 | 1/30/2007 | P | CANC |
Troy Cobbley
|
|
|
Per Terry the test is not ready today because the test pump had a malfunction.
|
INSP-Supply line flush | 1/22/2007 | 1/23/2007 | 1/23/2007 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed for the west buildings.
|
CHANGE STATUS TO (ISS) | | | 1/19/2007 | | DONE |
|
|
|
no fee, plans picked up
|
(F) Reprint permit | | | 1/19/2007 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/17/2007 | | PASS |
|
|
|
|
Inspection Record Card- Fire | 1/17/2007 | | 1/17/2007 | | PASS |
|
|
|
|
Permit Ready to Issue | | | 1/17/2007 | | PASS |
|
|
|
|
Plan assigned to (OutSourced) | 1/5/2007 | | 1/17/2007 | | PASS |
|
|
|
1/17/2007 11:50:44 CMC - activity updated through activity FIRA22 from case FIR06-00755.
|
INSP-Sprinkler Rough-in | 1/16/2007 | 1/16/2007 | 1/16/2007 | P | FAIL |
Forrest France
|
|
|
UG fire supply line is NOT approved for cover as the trenches are backfilled to the point that a sufficient inspeciton cannot be performed due to piping concealment. Contractor needs to expose the installation for viewing and request an additional inspection.
|
Sprinkler Plan Check | 1/5/2007 | | 1/11/2007 | | |
|
|
|
Plan review by Bryan Johson
|
INSP-Sprinkler Rough-in | 1/10/2007 | 1/10/2007 | 1/10/2007 | P | PART |
Troy Cobbley
|
|
|
See the city approved plans for the area of underground piping that can covered.
|
Telephone call | | | 1/10/2007 | | DONE |
|
|
|
Telephone call from John of Commercial Fire Protection inquiring about a request for inspection for cover of new underground supply. Informed John that a partial approval is all that could be granted at this stage of the project. Final approval would be up to the field inspector to verify approved plans and scope of work.
|
Case Summary | | | 1/5/2007 | | |
|
|
|
|
Miscellaneous action | | | 1/4/2007 | | |
|
|
|
plan modification accepted per Scott A.
|
Issue and Print Permit | | | 1/3/2007 | | |
|
|
|
|
Inspection Record Card- Fire | 12/14/2006 | | 12/14/2006 | | DONE |
|
|
|
|
Telephone call | | | 12/14/2006 | | DONE |
|
|
|
t/c w John at Commercial Fire ###-#### - permit ready and fees given ($150.00)
|
Permit Ready to Issue | | | 12/14/2006 | | DONE |
|
|
|
|
Sprinkler Plan Check | | | 11/17/2006 | | PASS |
|
|
|
Passed with conditions to be verified by inspector. Conditions of Approval:
The contractor may proceed on the condition as follows, a complete set of as-built re-submittals are to be submitted prior to final acceptance of this scope of work. It is noted that 10" underground not 6" will be installed leading to the new modified riser locations. The risers will include an approved back flow device forward flow assembly in accordance with NFPA 13 sec. 16.2.5. Red line drawings shall be maintained through the progression of this project for the field inspector's use.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/2006 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/20/2006 | | |
|
|
|
|
Application DENIED | | | 10/3/2006 | | FAIL |
|
|
|
Application denied . Faxed denied application to contractor. Resubmittal requried of full size, scaled drawings, minimum of 3 sets, water flow documentation required.
|
Telephone call | | | 10/3/2006 | | DONE |
|
|
|
tlk to brook nelson ###-#### that permit has been denied andneeds to be picked up
|
Application received | | | 9/29/2006 | | |
|
|
|
|
INSP-Final Inspection | 1/19/2007 | 1/22/2007 | | A | |
|
|
|
John ###-####
|
Pending Assignment by SAM | 9/29/2006 | | | | |
|
|
|
|
Sprinkler Plan Check | 10/3/2006 | | | | PEND |
|
|
|
|