Case Summary | | | 11/29/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/26/2014 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 10/20/2014 | 10/21/2014 | 10/21/2014 | A | PART |
Forrest France
|
|
|
Requesting Inspector walk through before final inspection is requested. Phone #: ###-#### Inspection requested via web by Keith Olstrom *Completed initial walkthrough- noted some areas in need of adjustment or revision, discussed testing schedlue, project finish, etc.
|
Miscellaneous action | | | 7/16/2014 | | DONE |
|
|
|
Stephanie Cobbley emailed to let me know she had been informed that the detector bases have independant bases form the smoke detectors. She wanted to know if there was an additional charge for the addresses and could she note them on as built drawings. I informed her that I felt the bases were part of the detector assembly so no additional charge and that as built documentation was adequate.
|
Permit Ready to Issue | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 7/14/2014 | | 7/14/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 7/11/2014 | | 7/11/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 7/11/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 7/11/2014 | | 7/11/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 7/11/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Application received | | | 7/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 10 2014 10:01AM
|
FIR-Aging Inspection | 8/10/2020 | 8/10/2020 | | | |
Jim Page
|
|
|
|