INSP-Final Inspection | 2/18/2019 | 2/19/2019 | 2/19/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
We would like to perform this in conjunction with other BLD fire inspections. Please call Randy if there are questions. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | PASS |
Jim Page
|
|
|
Rough in for overhead sprinkler piping approved for cover.
RANDY COURTWRIGHT Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
Issue and Print Permit | | | 1/28/2019 | | DONE |
|
|
|
|
Intake Approval | | | 1/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 1/25/2019 | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 1/25/2019 | | 1/25/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/25/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 1/25/2019 | | DONE |
|
|
|
met
|
Application received | | | 1/23/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2019 7:10AM
|