INSP-Final Inspection | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for scope of work complete.
Rick Phone #: ###-####
|
INSP-Sprinkler Rough-in | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | PEND |
Jim Page
|
|
|
Rough to cover inspection for overehad fire sprinkler piping in scope of work complete, approved for cover.
|
Issue and Print Permit | | | 2/25/2019 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/21/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/21/2019 | | 2/21/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Sprinkler Plan Check | 2/21/2019 | | 2/21/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Permit Ready to Issue | | | 2/21/2019 | | DONE |
|
|
|
met
|
Sprinkler Plan Check | 2/12/2019 | | 2/13/2019 | | FAIL |
Mark Stumbaugh
|
|
|
No building permit issued for this project.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 2/12/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Intake Approval | | | 2/12/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Corrections Needed
|
Intake Approval | | | 2/12/2019 | | FAIL |
Mark Stumbaugh
|
|
|
Items in first submittal not addressed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Plan resubmittals received | | | 2/12/2019 | | PASS |
Mark Stumbaugh
|
|
|
|
Plan assigned to (Stumbaugh) | 2/12/2019 | | 2/12/2019 | | DONE |
Mark Stumbaugh
|
|
|
|
Application received | | | 2/11/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 11 2019 1:30PM
|