INSP-Final Inspection | 3/27/2019 | 3/28/2019 | 3/28/2019 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Phone #: ###-#### Inspection requested via web by Ken Webster
|
INSP-Final Inspection | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | NR |
Troy Cobbley
|
|
|
I arrived and found that the existing fire alarm panel has been replaced apparently without permits by another contractor. So no testing was performed. Phone #: ###-#### Inspection requested via web by Ken Webster
|
INSP-Final Inspection | 2/25/2019 | 2/25/2019 | 2/25/2019 | P | FAIL |
Jim Page
|
|
|
Could not verify unit shutdown after initial smoke detector test, HVAC unit appears to be de-energized. Fire alarm panel has numorous issues, panel is showing a trouble with random characters showing up on screen, panel will not annunciate with troubles or supervisory signals. Monitoring was not verified during inspection.
Tom Phone #: ###-####
|
Issue and Print Permit | | | 2/25/2019 | | DONE |
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/22/2019 | | DONE |
|
|
|
Quick permit passed. No comments. Release delayed because applicant did not provide the associated building permit number on their application. Numerous current building permits at this site so hard to tell which permit is was associated with. Applicant finally provided correct number.
|
Permit Ready to Issue | | | 2/22/2019 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/19/2019 | | 2/19/2019 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/19/2019 | | PASS |
|
|
|
|
Alarm Plan Check | 2/19/2019 | | 2/19/2019 | | PASS |
Lee G Meredith
|
|
|
|
Application received | | | 2/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 17 2019 8:17AM
|