Information based on query as of Friday, May 17, 2024.
Permit Information
Permit NumberBLD05-00128
StatusExpired
Name RESOURCE MANAGEMENT
Site Address 1510 N 13TH ST
Project NameHyde Park Historic Renovation
Customer Number 
ePlanReviewNo
Description
HYDE PARK HISTORIC RENOVATION (SHELL ONLY) To reconstruct, renovate and remodel an exist historic building for future multi-tenant commercial and a single family residence. Work to include adding a new full basement, concrete floors, exterior walls, new windows, doors and related site improvements. The new structure will be constructed to appear from the outside, similar to the original residence. All construction per the approved plans and attached comment list. NOTE: This building is fully fire sprinklered. This is a shell building only, separate plans, permits and certificate of occupancies must be obtained to finish and occupy each tenant space in this building. (PLAN MODIFICATION 1/3/2006) To add to the basement 400 square feet of new interior floor area along with 429 square feet of covered exterior patio area. To add to the second floor 258 square feet of interior floor area and 650 square feet of exterior balcony area. MJP DRH02-00224. (PLAN MODIFICATION 1/29/08). To add 190 square feet of new interior floor area to the 2nd floor, install elevator shaft to service 3 levels, enlarge front entry canopy and add exterior fencing. BA 325
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Expired/Cancelled3/17/20143/17/20143/17/2014 FAIL
DetailsBob Archibald
No requests for required inspections. No activity or contractors on site has exceeded time limitations on permit since renewal.
BLD-Aging Inspection12/5/201312/5/201312/10/2013 NR
DetailsBob Archibald
No request for inspections. No new activity at site.
BLD-Aging Inspection9/5/20139/5/20139/9/2013 NR
DetailsBob Archibald
No request for inspection
BLD-Conference5/28/20135/29/20135/29/2013APEND
DetailsTony Young
status review,, 325 in charge of
BLD-Conference5/28/20135/29/20135/29/2013APEND
DetailsTony Young
status review
FIRE-Conference2/19/20132/21/20132/21/2013ADONE
DetailsForrest France
On site conference with contractor regarding project related fire alarm and sprinkler trade work, finish schedule, plan review, conditions for occupancy, IFC and NFPA requirements.
BLD-Other2/19/20132/19/20132/19/2013APEND
DetailsBob Archibald
Conference with Noah on requirements to obtain letter of compliance on shell. No occupancy approved.
BLD-Aging Inspection12/4/201212/4/201212/11/2012 PEND
DetailsTony Young
DOC - Permit Expired  2/4/2011 DONE
DetailsBob Archibald
Spoke with Brian, superintendant, and informed him of outstanding issues and that permit would have to be reactivated to obtain final inspection sign off.
BLD-Conference1/3/20111/3/20111/3/2011APASS
DetailsBob Archibald
Spoke with architect Larry Sundell and also left voice message with Bill Strack. Project completion required by January 31st or permit will be expired.
BLD-Conference11/15/201011/15/201011/15/2010PFAIL
DetailsBob Archibald
Conference with Bradley (###-####) the superintendent and informed him that this permit must have a final inspection prior to January 1, 2011.
Failure to complete remaining items required for a final will result in expiration of permit
BLD-Aging Inspection11/8/201011/8/201011/9/2010 PEND
DetailsTony Young
325 is handling this
BLD-Aging Inspection9/8/20109/8/20109/9/2010 PEND
DetailsTony Young
325 in charge of
BLD-Aging Inspection7/7/20107/7/20107/7/2010 PEND
DetailsTony Young
BLD-Conference5/7/20105/7/20105/7/2010PPART
DetailsBob Archibald
Status unchanged only minor improvements.
BLD-Aging Inspection4/19/20104/19/20104/20/2010 PEND
DetailsTony Young
DOC - Permit Expired4/20/20104/20/20104/20/2010ACANC
DetailsTony Young
BLD-Conference2/11/20102/11/20102/11/2010PPART
DetailsBob Archibald
Discussed with new superintendant requirements for obtaining a final on shell permit. No noticable improvements since last inspection (1 worker).
BLD-Aging Inspection11/20/200911/20/200911/27/2009 PEND
DetailsTony Young
BLD-Aging Inspection9/9/20099/9/20099/15/2009 PEND
DetailsTony Young
BLD-Other7/9/20097/9/20097/9/2009PPART
DetailsBob Archibald
Reviewed site, finish work in progress (Slow)
BLD-Other2/5/20092/5/20092/5/2009APART
DetailsBob Archibald
Slow progress. Finish work going on. Further discussion of purchasing adjavent building.
BLD-Conference12/1/200812/1/200812/1/2008PPART
DetailsBob Archibald
Conference with owner and contractor on requirements for final. Provided occupancy request card for signatures.
BLD-Aging Inspection11/10/200811/10/200811/14/2008 DEFR
DetailsTony Young
325 is taking care of this
BLD-Conference9/10/20089/10/20089/10/2008PPART
DetailsBob Archibald
Site conference with mechanical inspector and job super on duct openings and rated construction. No openings/penetrations allowed in stair enclosure from basement to first floor.
BLD-Other7/16/20087/16/20087/16/2008APART
DetailsBob Archibald
Review of basement and main floor. still have outstanding issues on mechanical systems and exterior windows (COA). Also discussed fire alarm progress and relocation of sprinkler lines. Fire blocking and south soffit made ok sheetrock installation in progress.
BLD-Framing/Rough-in5/23/20085/23/20085/23/2008PPART
DetailsBob Archibald
CN issued for cover of basement and main floor, reinspection required prior to complete cover.
BLD-Other5/23/20085/23/20085/23/2008PPASS
DetailsBob Archibald
Exterior patio stairs to upper level made ok rise/run.
BLD-Other5/5/20085/5/20085/5/2008PPART
DetailsBob Archibald
Work in progress (slow) noncomplying stairway to upper patio has been removed. Electrical contractor on site performing work in basement mechanical room, service drop on north end has been run underground and violtions corrected so that Idaho Power can contect new service drop to building.Plans for 2nd floor are still under review (pending fire and structural).
BLD-Conference4/23/20084/23/20084/23/2008APART
DetailsBob Archibald
Phone conference with Noah on elevator shaft requirements. State regulates car and mechanics.
BLD-Other4/1/20084/1/20084/1/2008PPART
DetailsBob Archibald
Elevator shaft framing approved for cover.
BLD-Other3/4/20083/4/20083/4/2008PFAIL
DetailsBob Archibald
CN issued on outstanding issues. Reviewed site with Noha phone conference with Bill.
BLD-Aging Inspection2/18/20082/18/20082/21/2008 DEFR
DetailsTony Young
325 is taking care of this
BLD-Other2/20/20082/20/20082/20/2008PPART
DetailsBob Archibald
Review of elervator shaft construction and overall status of construction. 1st story shaft construction in progress. 1 carpenter on site, no new progress elsewhere.
BLD-Other12/5/200712/5/200712/5/2007AFAIL
DetailsBob Archibald
CN issued for south soffit, 1 hour construction not verified before covering. Inspection opening requested.
BLD-Conference12/4/200712/4/200712/4/2007PPART
DetailsBob Archibald
Conference with architect on revised plan requirements.
BLD-Other11/16/200711/16/200711/16/2007PPART
DetailsBob Archibald
Welding inspection report from G3 all welding in compliance to date. Exterior railing welding to be completed.
BLD-Other11/13/200711/13/200711/13/2007AFAIL
DetailsBob Archibald
Phone conference with Noah on stair run requirements 11" minimum required, 10" not allowed on exterior stairs to patio. Correction Required.
BLD-Conference11/1/200711/1/200711/1/2007AFAIL
DetailsBob Archibald
CN issued requesting revised plans be submitted to plan review on as builts and DR approvals to date. No framing cover will be allowed until submitted and approved.
BLD-Aging Inspection10/22/200710/22/200710/29/2007 PEND
DetailsTony Young
325 taking care of
BLD-Other5/24/20075/24/20075/24/2007APART
DetailsBob Archibald
Resubmittals approved and plans are ready to be picked up.
BLD-Concrete4/20/20074/20/20074/20/2007PPART
DetailsBob Archibald
Parapet wall on north patio also reviewed furr out framing in basement.
BLD-Other3/29/20073/29/20073/29/2007PPART
DetailsBob Archibald
Conference on riser heights, headroom clearance in main building and resubmittals
BLD-Concrete3/23/20073/23/20073/23/2007APART
DetailsBob Archibald
Interior concrete stairs/landing (Headroom Clearance to be addressed). Exterior patio wall, special inspection performed
BLD-Foundation3/12/20073/12/20073/12/2007PPART
DetailsBob Archibald
Last section of north wall. special inspection and engineering review had been performed. Remined Bill that plan review still waiting on resubmittals.
BLD-Other2/14/20072/14/20072/14/2007APART
DetailsBob Archibald
Site review, conference with contractor on roof/soffit, 2nd story windows on south end, stairs etc..
BLD-Other2/7/20072/7/20072/7/2007PPART
DetailsBob Archibald
Site review.
BLD-Wall cover12/19/200612/19/200612/19/2006PPART
DetailsBob Archibald
Exterior shear walls, CN issued.
BLD-Conference11/15/200611/15/200611/15/2006PPART
DetailsBob Archibald
Met with architect and discussed requirements for resubmittals for all trades/aspects of structure, new structural, architectual, electrical, plumbing and mechanical drawings required. Framing crew has been hired and framing is progressing quickly on exterior of structure.
BLD-Concrete11/8/200611/8/200611/8/2006PPART
DetailsBob Archibald
Remainder of 2nd floor concrete slab placed today. Requested revised details reflecting changes and Historic approvals.
BLD-Conference10/18/200610/18/200610/18/2006PPART
DetailsBob Archibald
Discussion on schedule and current status. Reinforcing steel being placed for secound floor concrete placement.
BLD-Other10/4/200610/4/200610/4/2006PPART
DetailsBob Archibald
Ground level floor slab placed last week special inspection and engineer reviewed prior to concrete placement. 5/8ths type X gypsum applied to exterior south wall and OSB placed on exterior, shear nailing has not been completed(1st floor level only).
BLD-Other9/22/20069/22/20069/22/2006PPART
DetailsBob Archibald
Site conference with Bill Strack and Larry Sundell on required resubmittals reflecting changes approved by historic commision and as builts, also discussed stair requirements, rise/run. Phone conference with engineer on south wall requirements to meet shear and fire rating. OSB will be removed gyp rock installed and OSB applied over gyp and nailed at 4" oc.. 1st floor slab to scheduled to be placed 9/25/06.
BLD-Other9/6/20069/6/20069/6/2006APART
DetailsBob Archibald
COnference with engineer of record and Bill Strack on concrete slabs, shear walls and misc. details. Basement floor slab was placed 9/01/06 except northeast corner, exterior wall framing scheduled to commence with 1st and 2nd floor concrete placement in concurance. Special inspection required on all concrete, reinforcing steel and site welding.
BLD-Foundation7/12/20067/12/20067/12/2006PPART
DetailsBob Archibald
Concrete placement on remaining north foundation wall placed, special inspector on site. Perimeter footing/foundation now complete.
Code Occupancy Approval6/30/20066/30/20067/3/2006PCANC
DetailsWm. Michael Meloy
BLD-Conference6/6/20066/6/20066/6/2006APART
DetailsBob Archibald
Slow progress, only one worker on site. North foundation wall framing nearly complete and concrete placement scheduled for the near future. Additional structural steel framing has been placed and 1st floor pan deck installation near completion.
BLD-Footing4/6/20064/6/20064/6/2006APASS
DetailsBob Archibald
Remaining north wall footing placed 3/31/06, special inspection was provided. Foundation wall reinforcing being placed at this time.
BLD-Other3/24/20063/24/20063/24/2006PPART
DetailsBob Archibald
Construction of footing formwork for north wall in progress.
BLD-Other3/3/20063/3/20063/8/2006PPART
DetailsBob Archibald
Metal pan deck being placed for floors, Foundation walls have been backfilled against (west, south and part of east). Excavation in progress for north foundation wall.
BLD-Conference2/10/20062/10/20062/10/2006PPART
DetailsBob Archibald
Issued CN requesting resubmittals (structural and architectual). Also required separate application ands permit for patio on north end of structure.
BLD-Foundation2/1/20062/1/20062/1/2006APART
DetailsBob Archibald
Remainder of south wall and east wall placed, both engineer and special inspection had reviewed. This concrete placement completes 3/4 of footing and foundation with only the north wall remaining to be placed.
BLD-Footing1/23/20061/23/20061/23/2006PPART
DetailsBob Archibald
Remainder of south wall and south 1/2 of east wall formed and ready for concrete placement. When placed this will complete 2/3rds of footing and foundation. Work in progress on northeast corner to plumb structural steel.
BLD-Footing12/2/200512/2/200512/2/2005APART
DetailsBob Archibald
Remainder of 13th street, northwest corner, footing has been placed and special inspection was provided. Excavation and formwork placement for footing in progress on southeast corner of project.
BLD-Concrete11/18/200511/18/200511/18/2005PPART
DetailsBob Archibald
1st floor pan deck being installed, footing being formed at northwest corner.
BLD-Concrete11/10/200511/10/200511/10/2005PPART
DetailsBob Archibald
Basement slab placement in progress, observed special inspection report and witnessed concrete testing.
BLD-Foundation11/2/200511/2/200511/2/2005PPART
DetailsBob Archibald
Met with structural engineer and reviewed foundation wall reinforcement on southwest corner of building, concrete placement scheduled for 11/03/05. Requested a entire stamped engineering package when concrete work was completed as design requirements had changed. Craig said he would provide.
BLD-Foundation10/28/200510/28/200510/28/2005PPART
DetailsBob Archibald
Foundation reinforcement and forms in place, special inspection has been performed and passed (1/2 of south wall and 1/2 of 13th street wall). Also received special inspection reports on welding, concrete breaks and reinforcing inspection
BLD-Footing10/11/200510/11/200510/11/2005PPART
DetailsBob Archibald
Reinforcing steel being placed in south west corner of structure ~ half the length of 13th street and have the length of south wall. Special inspection has been requested/scheduled by permit holder.
BLD-Footing9/28/20059/28/20059/28/2005PPASS
DetailsBob Archibald
Special inspection has been performed on the 4 main interior column footing pads. Special inspection reported reinforcing steel exceeded approved plans. Concrete placement scheduled for 9/29/05.
BLD-Other9/27/20059/27/20059/27/2005PPASS
DetailsBob Archibald
Historic Preservation Commission approved DRH05-00290 for the construction of a second story patio and brick support wall on the north end of this structure. Resubmittals must be provided to plan review for code anaysis.
BLD-Conference9/23/20059/23/20059/23/2005P 
DetailsBob Archibald
Excavation and formwork in progress for the 4 center column footings. Concret placement scheduled for 9/27/05.
BLD-Other9/16/20059/16/20059/16/2005PPART
DetailsBob Archibald
Excavation near completion. Reported that pit run would be delivered later for footing base.
BLD-Other9/9/20059/9/20059/9/2005PPART
DetailsBob Archibald
Cable bracing installed for stability of structural frame. No new excavation in progress or placement of formwork for footings.
BLD-Conference9/1/20059/1/20059/1/2005PPART
DetailsBob Archibald
Site conference with Bill, informed him that schedule must be increased as project is behind schedule. Excavation of basement in progress and Bill informed me that 13th street side foundation will be placed 1st and frame should be on foundation by 15th with remainder to follow shortly after.
BLD-Other8/26/20058/26/20058/26/2005PPART
DetailsBob Archibald
Excavation of basement in progress, slow.Steel frame outfitted with jacks and has been slightly raised to finished floor elevation.
BLD-Conference8/1/20058/1/20058/1/2005PPART
DetailsBob Archibald
Met with super, architect and engineer on site to resolve skylight issue. Engineer provided design for structural framing.
BLD-Other7/28/20057/28/20057/28/2005PPART
DetailsBob Archibald
Site visit. Single story portion of structure on south end has been demo'd and removed, excavation for basement in progress. Structural steel of 2 story near completion.
BLD-Other7/20/20057/20/20057/20/2005APART
DetailsBob Archibald
Issued CN on south basement walls listing requirements for window installation. Structural steel roofing near completion.
BLD-Other7/15/20057/15/20057/15/2005PPART
DetailsBob Archibald
Site review of construction progress to date. Conference with Bill Strack. Structural steel installation near complete in two story roof area, demolition of exterior patio area and removal of roof covering on south single story area in progress. Requested wall stabalization in patio area , northwest corner, diagonal bracing and bearing.
BLD-Other6/29/20056/29/20056/29/2005PPART
DetailsBob Archibald
Reinforcing of roof still in progress.
BLD-Other6/23/20056/23/20056/23/2005PPART
DetailsBob Archibald
Site visit. Reinforcing of roof in progress, new framing members being installed along-side existing members. Phone conference with Bill informed him all resubmittals must have signature on wet stamp( architect/engineer).
BLD-Conference6/17/20056/17/20056/17/2005APART
DetailsBob Archibald
Conference on below grade windows on southside of structure. Spoke with Mike P. and Jeff N., below grade windows would be allowed on south side provided windows are entirely below finished grade and provided with a protective screening over window well. Window well must remain entirely on property and not cross adjacent property line.Windows would not be a required means of egress. Explained these conditions to Bill S. and requested a resubmittal if windows are to be installed.
BLD-Other6/17/20056/17/20056/17/2005APART
DetailsBob Archibald
Notes for activities prior to issuance of this permit are contained in permit # MIS05-00013.