Description
(PETROGLYPH ENERGY) (SUITE 500) (10-8-09) A PLAN MODIFICATION IS APPROVED TO ELIMINATE THE SHOWER AND LOCKER ROOM FROM THE PROJECT, ENLARGE THE PROPOSED NEW RESTROOM, AND DOWNGRADE THE EXISTING 1-HR FIRE-RESISTANCE-RATED CORRIDOR TO A NON-RATED CORRIDOR. QUICK-RESPONSE SPRINKLERS ARE REQUIRED TO BE INSTALLED THROUGHOUT THE ENTIRE 5TH STORY IN LIEU OF MAINTAINING THE CORRIDOR AS A 1-HR FIRE-RESISTANCE-RATED CORRIDOR. THE FIRE SPRINKLER WORK IS COVERED BY PERMIT FIR09-00561. This building is required to be fully fire sprinklered. To create a 10,185 square foot office tenant space from a larger space located on the 5th story. Work is to include a toilet room accessible to the disabled, interior nonbearing walls, interior windows, interior doors, millwork, and finishes. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. If the existing automatic sprinklers within this tenant space are not quick-response, they are required to be replaced with quick-response automatic sprinklers. The adjacent tenant space is not allowed to be occupied under this permit. The tenant who intends to occupy the adjacent tenant space is required to get its own Certificate of Occupancy before occupying that space. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/29/200910/30/200910/30/2009APASS
DetailsJim Storey
John Phone #: ###-#### perm final ok pending fire permit signed off for sprinkler head change out.
FIRE-Final Inspection10/28/200910/29/200910/29/2009PPASS
DetailsTroy Cobbley
Life safety passed.
BLD-Conference10/27/200910/27/200910/27/2009PDONE
DetailsForrest France
Regarding an existing fire smoke damper.
BLD-Framing/Rough-in10/7/200910/8/200910/8/2009APASS
DetailsJim Storey
john Phone #: ###-#### ok to cover ceilling ecept for at vav boxes to get plm insp.
BLD-Framing/Rough-in9/25/20099/28/20099/28/2009APASS
DetailsJim Storey
John Phone #: ###-#### ceillings ok to cover.
BLD-Conference8/31/20099/1/20099/1/2009APASS
DetailsJim Storey
John Phone #: ###-####
BLD-Conference8/26/20098/26/20098/26/2009PPASS
DetailsJim Storey
John Phone #: ###-####
BLD-Framing/Rough-in8/6/20098/7/20098/7/2009PPART
DetailsJim Storey
john Phone #: ###-#### ok pending ele aprovals in conf. rm restaroom and loby soffit.
BLD-Framing/Rough-in7/16/20097/17/20097/17/2009APART
DetailsJim Storey
john Phone #: ###-#### revised plan to be submitted to carl w for change in ada shower area. walls ok to cover.