BLD-Final | 12/6/2012 | 12/7/2012 | 12/7/2012 | A | PASS |
Tony Young
|
|
|
after 9:30//Peter Phone #: ###-####
|
FIRE-Final Inspection | 12/6/2012 | 12/6/2012 | 12/6/2012 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 10/5/2012 | 10/8/2012 | 10/8/2012 | A | FAIL |
Troy Cobbley
|
|
|
Remove the thumbturn dead bolt from the main exit (keyed is ok), replace the broken electrical cover at the sign, sprinkler heads are overspaced and need to be modified (this work requires a separate permit), provide access to the fire sprinkler riser room to verify annual inspection, repair exit signs and emergency lighting.
|
FIRE-Final Inspection | 10/4/2012 | 10/5/2012 | 10/5/2012 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. I contacted Peter and we agreed to reschedule for monday morning. I can find no record of a sprinkler permit for the changes that were needed per the previous conference. Peter stated the original contractor was no longer there and he did not know about sprinkler requirements.
|
FIRE-Final Inspection | 8/30/2012 | 8/31/2012 | 8/31/2012 | P | NH |
Forrest France
|
|
|
Peter Phone #: ###-####
|
BLD-Framing/Rough-in | 4/23/2012 | 4/23/2012 | 4/23/2012 | P | PART |
Tony Young
|
|
|
walls ok,,, contractyor said there was plastic under the slab for sill plate
|
BLD-Framing/Rough-in | 4/19/2012 | 4/20/2012 | 4/20/2012 | A | FAIL |
Tony Young
|
|
|
brad Phone #: ###-####,, need trades,, some interior walls ok with out mechanical
|
FIRE-Conference | 4/17/2012 | 4/17/2012 | 4/17/2012 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements with Brad. I noted that several of the sprinkler heads are overspaced. We discussed door hardware issues and fire extinguishers.
|
BLD-Conference | 4/12/2012 | 4/12/2012 | 4/12/2012 | P | FAIL |
Tony Young
|
|
|
STATUS CHECK,, to many possible issues,, requested all trades to meet on site for friday 13th,, under a mis permit
|