Permit Information
Permit NumberBLD12-01393
StatusFinaled
Name ESI
Site Address 7500 W FAIRVIEW AVE
Project NameWestgate Shopping Center- Exte
Customer Number 
ePlanReviewYes
Description
(**Shell and Core** - Westgate Shopping Center) Permit is to remodel the existing canopy that runs the length of the shopping center. Approval subject to compliance with approved plans, attached engineering, and DRH12-00117. Work includes: extending existing two hour area separation wall through the canopy, installation of new exterior lighting, infill existing windows with one hour wall, build out canopy columns, new roofing on the canopy, new paint on the canopy, and interior finishes in compliance with Ch. 8 of the 2009 IBC. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/9/201210/9/201210/9/2012PPASS
DetailsJim Sly
JP Phone #: ###-####
C/C issued.
DOC - Permit Finaled10/9/201210/9/201210/9/2012PPASS
DetailsJim Sly
BLD-Final10/8/201210/8/201210/9/2012PCANC
DetailsJim Sly
JP Phone #: ###-####
Re-sched...
FIRE-Final Inspection10/5/201210/8/201210/8/2012APASS
DetailsTroy Cobbley
Life safety passed. Inspector Jim Sly verified the installation of the insulation in the combustible concealed spaces. See previous inspection entrys.
BLD-Final10/5/201210/5/201210/5/2012PNR
DetailsJim Sly
JP Phone #: ###-####
Need Fire, Electr and Zoning. finals
BLD-Energy code compliance9/25/20129/26/20129/26/2012APART
DetailsJim Sly
Jp Phone #: ###-####
Roof element 1 and 2 are filled with insulation.
BLD-Framing/Rough-in9/21/20129/21/20129/21/2012PPART
DetailsJim Sly
JP ###-####
Roof element 1 and 3 framing ok and ready to fill with insulation. Element 2 (middle) filled with insulation and OK to cover.
BLD-Framing/Rough-in9/20/20129/21/20129/21/2012ACANC
DetailsJim Sly
jp Phone #: ###-####
BLD-Framing/Rough-in8/20/20128/20/20128/21/2012PPASS
DetailsJim Sly
Fire wall - -JP Phone #: ###-####
2 HR wall in front soffit area.....OK
FIRE-Final Inspection8/15/20128/16/20128/16/2012AFAIL
DetailsTroy Cobbley
Todays inspection was just for approval of the fire wall that was relocated so as not to interfere with the upright sprinkler protection inside of the exterior canopy. Wall location is ok with me as long as the building inspector is ok with it.
BLD-Conference8/15/20128/16/20128/16/2012ADONE
DetailsJim Sly
jp Phone #: ###-####
Verified location of 2hr wall in canopy OK so they can proceed.
FIRE-Conference8/15/20128/15/20128/15/2012PDONE
DetailsTroy Cobbley
I met with JP Burger/ESI about possible sprinkler protection in the parapats and at the new fire wall within the existing canopy. Approval from the architect is needed to move the fire wall and consultation with a fire sprinkler contractor is needed for the parapats.
BLD-Wall Bracing8/13/20128/14/20128/14/2012APART
DetailsJim Sly
JP Phone #: ###-####
Roof parapet ....Element 2 (center) Ok to cover.