BLD-Final | 12/12/2012 | 12/13/2012 | 12/13/2012 | A | PASS |
Dave Hannah
|
|
|
ron Phone #: ###-####
|
FIRE-Final Inspection | 12/12/2012 | 12/12/2012 | 12/12/2012 | P | PASS |
Forrest France
|
|
|
Fire life safety final approved.
|
BLD-Final | 11/8/2012 | 11/9/2012 | 11/9/2012 | A | PART |
Dave Hannah
|
|
|
call for access - Ron Phone #: ###-#### ok for temp occ ok for perm occ after other trades go perm
|
FIRE-Final Inspection | 11/8/2012 | 11/8/2012 | 11/8/2012 | A | PART |
Forrest France
|
|
|
Temp. occupancy granted with R. Gervais approval until 12/15/12. Final pending modifications to the existing building fire alarm system to accomodate adequate visual coverage at two locations.
|
FIRE-Final Inspection | 11/2/2012 | 11/5/2012 | 11/5/2012 | A | PART |
Forrest France
|
|
|
Fire life safety final pending modifications to the existing fire alarm system. Adjustments to maintatin notification coverage will be necessary due to the new floorplan. Remainder of fire life safety conditions are satisfactory.
|
FIRE-Final Inspection | 10/29/2012 | 10/29/2012 | 10/29/2012 | P | FAIL |
Forrest France
|
|
|
Type one hood failed to report to the FACP, modifications to the fire alarm system will be necessary to maintain coverage where new walls and partitions have been built, project related fire sprinkler permit needs called for inspection, noted one EM light to be repaired, relocate the K class PFE as discussed.
|
BLD-Framing/Rough-in | 9/5/2012 | 9/6/2012 | 9/6/2012 | A | PASS |
Dave Hannah
|
|
|
ron - call for access Phone #: ###-####
|