Information based on query as of Sunday, May 19, 2024.
Permit Information
Permit NumberBLD13-03257
StatusIssued
Name CALLIES CONSTRUCTION
Site Address 1075 E PARK BLVD
Project NameBoise State University
Customer Number 
ePlanReviewNo
Description
(BOISE STATE UNIVERSITY CLASSROOMS) A fire sprinkler system will be installed throughout this building in conjunction with this permit and will be used in lieu of rated corridors and to allow unprotected openings in the West exterior wall. To remodel an 11,830 square foot area within an existing 23,200 square foot one story building for a new classroom tenant space for students above the 12th grade. Work is to include interior nonbearing walls, 2 multi-user restrooms accessible to the disabled, an exterior concrete ramp accessible to the disabled, and platforms for new roof top HVAC units. Three new roof top HVAC units will be provided. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The entire building will have a fire sprinkler system installed in conjunction with this permit. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Since combustible materials are exposed within the attic space, the attic is required to have fire sprinkler protection. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/16/20144/17/20144/17/2014APASS
DetailsDave Hannah
Kyle Phone #: ###-####
FIRE-Final Inspection4/16/20144/17/20144/17/2014APASS
DetailsForrest France
Verified remainder of work is completed. Fire life safety final approved.
BLD-Final3/26/20143/27/20143/27/2014PPART
DetailsDave Hannah
Kyle Phone #: ###-#### ok for temp occ ok for perm occ after fire gos perm
FIRE-Final Inspection3/26/20143/27/20143/27/2014APART
DetailsForrest France
Fire life safety final pending installation of a knox box per plan review notes. Remainder of corrections and adjustments completed. Temporary occupancy approved.
FIRE-Final Inspection3/26/20143/26/20143/26/2014ANR
DetailsForrest France
Project related FIR trade work including the fire alarm and sprinkler permit finals pending, need to post signage at the main entry/exit, remove mag lock or provide relay to the fire alarm system at the east exit door, post signage at the courtyard exit door, missing knox box, post signage at the riser room door, noted some exit signs not functional on battery backup. Discussed project schedule for permit finals.
BLD-Final3/25/20143/25/20143/25/2014PNR
DetailsDave Hannah
Kyle Phone #: ###-####
BLD-Ceiling Grid Inspection3/10/20143/10/20143/10/2014PPASS
DetailsJim Storey
Kyle Dunstan Phone #: ###-####
BLD-Ceiling Grid Inspection3/6/20143/7/20143/7/2014AFAIL
DetailsDave Hannah
Kyle Phone #: ###-#### new grid needs to be cliped or install spradder bars at perm.
BLD-Framing/Rough-in2/14/20142/14/20142/14/2014PCANC
DetailsJim Sly
kyle Phone #: ###-####
Dave Hannah called me and said it was done.
BLD-Framing/Rough-in2/11/20142/11/20142/12/2014PPASS
DetailsDave Hannah
KYLE Phone #: ###-####
BLD-Footing1/22/20141/22/20141/22/2014PPASS
DetailsDave Hannah
dan Phone #: ###-####