Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberBLD13-03585
StatusFinaled
Name ANDERSEN CONSTRUCTION CO
Site Address 12065 W OVERLAND RD
Project NameCantabria Development
Customer Number 
ePlanReviewNo
Description
(CANTABRIA DEVELOPMENT - BLDG 6) - To construct a new 3,668 sq. ft., two story, Four unit, apartment building. Units 'A' have one bedroom, one den, and two bathrooms. Units 'B' have two bedrooms, and two bathrooms. All 4 dwelling units have their own independent exit. All construction per the approved plans, attached plan review report, and all other reviewing agencies approvals. One hour fire-partition separations are required between dwelling units. This building is required to be fire sprinklered. The fire sprinkler system shall be per NFPA 13R as regulated by the fire department. DRH13-00337 Per Planning and Zoning. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection3/7/20163/7/20163/8/2016 PASS
DetailsMike Jordan
BLD-Aging Inspection1/4/20161/4/20161/4/2016 PASS
DetailsMike Jordan
BLD-Aging Inspection10/15/201510/15/201510/15/2015 PASS
DetailsMike Jordan
BLD-Final8/3/20158/3/20158/3/2015PPART
DetailsPhil Shearer
OK for temp occupancy.
FIRE-Final Inspection7/27/20157/28/20157/28/2015APASS
DetailsTroy Cobbley
Life Safety Passed
FIRE-Final Inspection7/23/20157/24/20157/24/2015ACANC
DetailsTroy Cobbley
To be rescheduled for monday
BLD-Energy code compliance5/27/20155/28/20155/28/2015PPASS
DetailsMike Jordan
insulation inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Framing/Rough-in5/22/20155/26/20155/26/2015PPASS
DetailsJim Sly
rough frame inspection Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Wall Bracing4/23/20154/23/20154/23/2015PPASS
DetailsMike Jordan
exterior shear Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Wall Bracing4/8/20154/9/20154/9/2015APASS
DetailsMike Jordan
interior shear 2nd floor Phone #: ###-#### Inspection requested via web by Mel Rawlinson
BLD-Wall Bracing3/30/20153/30/20153/30/2015PPASS
DetailsMike Jordan
Tyler// 1st floor interior sheer Phone #: ###-####
BLD-Energy code compliance2/25/20152/26/20152/26/2015APASS
DetailsMike Jordan
Vicki Phone #: ###-####
BLD-Foundation2/19/20152/19/20152/19/2015PPASS
DetailsMike Jordan
Memuel Phone #: ###-####
BLD-Footing2/17/20152/17/20152/17/2015PPASS
DetailsMike Jordan
Menuel Phone #: ###-####