BLD-Final | 8/9/2016 | 8/9/2016 | 8/9/2016 | A | PASS |
Jim Storey
|
|
|
final ok
|
FIRE-Final Inspection | 7/25/2016 | 7/26/2016 | 7/26/2016 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. The lack of floor slope in the fire pump room hasa been approved by Assistant Chief Ron Johnson
|
BLD-Final | 7/21/2016 | 7/22/2016 | 7/22/2016 | P | NR |
Jim Storey
|
|
|
Clint Phone #: ###-#### need fire life safety final-ok for temp c of o
|
FIRE-Final Inspection | 7/21/2016 | 7/22/2016 | 7/22/2016 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is approved for 30 days with Scott's permission. For a final I need the project related fire alarm permit finaled which includes re-submittals and a map, and I need the building plan modifications for the revised fire pump room to be approved and any corrections implemented.
|
BLD-Conference | 5/25/2016 | 5/26/2016 | 5/26/2016 | P | CANC |
Troy Cobbley
|
|
|
|
FIRE-Conference | 5/17/2016 | 5/17/2016 | 5/17/2016 | P | DONE |
Troy Cobbley
|
|
|
After dicussing lack of slope in the FIre Pump Room with Scott Arellano I spoke to the project superintendant about the floor slope issue and that there would be no final sign off on the life safety until the floor had been sloped as per previous discussions.
|
BLD-Wall Bracing | 5/13/2016 | 5/16/2016 | 5/16/2016 | A | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | PASS |
Jim Storey
|
|
|
Matt-rebar pre pour slab on grade Phone #: ###-####
|
BLD-Concrete | 5/4/2016 | 5/5/2016 | 5/5/2016 | P | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-####
|
BLD-Energy code compliance | 4/29/2016 | 4/29/2016 | 4/29/2016 | P | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 4/26/2016 | 4/26/2016 | 4/26/2016 | P | PART |
Jim Storey
|
|
|
Matt Phone #: ###-#### ok to one side ada on mens room 12 push w/closer
|
BLD-Concrete | 4/21/2016 | 4/22/2016 | 4/22/2016 | A | PASS |
Jim Storey
|
|
|
Matt Phone #: ###-####
|
FIRE-Conference | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | DONE |
Troy Cobbley
|
|
|
Met sprinkler contractor and project superintendant and discussed job progress and floor slope in the fire pump room.
|
FIRE-Conference | 4/12/2016 | 4/12/2016 | 4/12/2016 | A | DONE |
Troy Cobbley
|
|
|
I spoke to the project superintendant about the NFPA 20 requirements for pitched floors, floor drains, emergency lighting and ventilation.
|
BLD-Footing | 3/24/2016 | 3/24/2016 | 3/24/2016 | P | PART |
Jim Storey
|
|
|
Matt-would like as late as possible Phone #: ###-####slab on grade
|
BLD-Other | 3/16/2016 | 3/17/2016 | 3/17/2016 | A | PASS |
Jim Storey
|
|
|
fire rated panelling // matt Phone #: ###-#### pannels listing pass
|
BLD-Foundation | 2/25/2016 | 2/25/2016 | 2/25/2016 | P | PASS |
Jim Storey
|
|
|
Matt-pre-slab on grade Phone #: ###-####
|