**Project Management-Ron Hill** (ALBERTSON’S HANGAR) Permit is to construct a new 19,990 square foot Group II aircraft hangar. This building is fully fire sprinklered to comply with Ch. 4 Special Requirements for Aircraft Hangers. This building is complying with Interior Lighting for the required additional energy code package. The foundation and site work for this structure was permitted under BLD15-03897. Approval contingent upon adhering to the approved plans on file and attached engineering. Work to include: construction of new premanufactured metal building, installation of 2 hour UL rated exterior metal panels, new plumbing, new electrical, new mechanical, and interior finishes. This building will be fire sprinklered as required by section 412.4.6 in accordance with NFPA 409. **TLW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final8/9/20168/9/20168/9/2016APASS
DetailsJim Storey
final ok
FIRE-Final Inspection7/25/20167/26/20167/26/2016APASS
DetailsTroy Cobbley
Life safety passed. The lack of floor slope in the fire pump room hasa been approved by Assistant Chief Ron Johnson
BLD-Final7/21/20167/22/20167/22/2016PNR
DetailsJim Storey
Clint Phone #: ###-#### need fire life safety final-ok for temp c of o
FIRE-Final Inspection7/21/20167/22/20167/22/2016APART
DetailsTroy Cobbley
A temporary occupancy is approved for 30 days with Scott's permission. For a final I need the project related fire alarm permit finaled which includes re-submittals and a map, and I need the building plan modifications for the revised fire pump room to be approved and any corrections implemented.
BLD-Conference5/25/20165/26/20165/26/2016PCANC
DetailsTroy Cobbley
FIRE-Conference5/17/20165/17/20165/17/2016PDONE
DetailsTroy Cobbley
After dicussing lack of slope in the FIre Pump Room with Scott Arellano I spoke to the project superintendant about the floor slope issue and that there would be no final sign off on the life safety until the floor had been sloped as per previous discussions.
BLD-Wall Bracing5/13/20165/16/20165/16/2016APASS
DetailsJim Storey
Matt Phone #: ###-####
BLD-Foundation5/11/20165/12/20165/12/2016APASS
DetailsJim Storey
Matt-rebar pre pour slab on grade Phone #: ###-####
BLD-Concrete5/4/20165/5/20165/5/2016PPASS
DetailsJim Storey
Matt Phone #: ###-####
BLD-Energy code compliance4/29/20164/29/20164/29/2016PPASS
DetailsJim Storey
Matt Phone #: ###-####
BLD-Framing/Rough-in4/26/20164/26/20164/26/2016PPART
DetailsJim Storey
Matt Phone #: ###-#### ok to one side ada on mens room 12 push w/closer
BLD-Concrete4/21/20164/22/20164/22/2016APASS
DetailsJim Storey
Matt Phone #: ###-####
FIRE-Conference4/19/20164/19/20164/19/2016PDONE
DetailsTroy Cobbley
Met sprinkler contractor and project superintendant and discussed job progress and floor slope in the fire pump room.
FIRE-Conference4/12/20164/12/20164/12/2016ADONE
DetailsTroy Cobbley
I spoke to the project superintendant about the NFPA 20 requirements for pitched floors, floor drains, emergency lighting and ventilation.
BLD-Footing3/24/20163/24/20163/24/2016PPART
DetailsJim Storey
Matt-would like as late as possible Phone #: ###-####slab on grade
BLD-Other3/16/20163/17/20163/17/2016APASS
DetailsJim Storey
fire rated panelling // matt Phone #: ###-#### pannels listing pass
BLD-Foundation2/25/20162/25/20162/25/2016PPASS
DetailsJim Storey
Matt-pre-slab on grade Phone #: ###-####