Information based on query as of Saturday, May 11, 2024.
Permit Information
Permit NumberBLD16-02734
StatusFinaled
Name LANSING INVESTMENT COMPANY LLC
Site Address 5878 W FRANKLIN RD
Project NameNerfed
Customer Number 
ePlanReviewYes
Description
(NERFED) **DO NOT FINAL UNTIL BLD16-01070 IS COMPLETED **Plan Modification for interior obsticals for tenant 4-14-17 ajs****Permit for new occupancy use within an existing space (See BLD16-01070). See building official letter in shell permit for alternate approvals for this project. Scope of work shall include Exit signage, exit discharge lighting, door hardware, restroom upgrades. This building is NOT fire sprinklered. This building is a separated use building. **ajs**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/6/20176/6/20176/6/2017PPASS
DetailsMike Jordan
The 3hr. wall has been completed on adjacent tenant. ok for perm occ.
BLD-Final4/17/20174/17/20174/17/2017PPART
DetailsMike Jordan
Phil Phone #: ###-####. OK for temp occ. the work on the 2hr. fire walls is completed. All mill thicknesses verified by special inspection. The 3hr. wall is completed on the nerfed side. Will be ok for perm occ. once the remainder of the 3hr. wall is completed on the usful glassworks side. All other issues for this tenant have been resolved.
FIRE-Final Inspection4/17/20174/17/20174/17/2017PPASS
DetailsTroy Cobbley
life safety passed
FIRE-Final Inspection3/28/20173/29/20173/29/2017AFAIL
DetailsTroy Cobbley
I performed a courtesy inspection since no IFC review comments had been provided. The corrections I found apply to all three BLD permits which include BLD16-01070, BLD16-02734 and BLD16-02747. BLD16-02747 was actually still in review status due to a plan modification. Corrections I noted are, new double doors not installed, existing door infilled in Corridor 12, opening infilled in Birthday Room, doors not shown, hardware not allowing direction of egress travel, non-compliant ADA hardware in egress path, door in egress path non-functional, egress path corridor blocked with storage, permanant walls installed that are not shown on the plans that also block view of exit signs, cloth mesh blocking view of exit signs, issues of foam, rubber tire storage, plastic inflatables and plastic barrels (quantity and storage arrangement) in the NERF tenant and the issues of large amounts of foam (mats) in the Gymnastic tenant., also one fire extinguisher was missing and another was mounted too high.