Information based on query as of Saturday, May 4, 2024.
Permit Information
Permit NumberBLD17-00386
StatusFinaled
Name PERKINS CONSTRUCTION
Site Address 2855 W LOCKHEED LN
Project NameCity of Boise ARFF BLDG
Customer Number17-01549
ePlanReviewYes
Description
(CITY OF BOISE AIR RESCUE & FIRE FIGHTING STATION)(AT BOISE AIRPORT) (**GREEN BUILDING - EXPEDITED REVIEW**) ""PLAN MODIFICATION TO INCLUDE LEAVING THE EXISTING COMPUTER LAB AND REVISE THE INTERIOR CONFIGURATION OF THE BUILDING"" There are two permits associated with thie Eplan case (BLD17-01549) Project shall comply with the 2012 International Green Construction Code as adopted by City of Boise. This project includes the remodel and expansion of the existing Air Rescue and Fire Fighting Station at the Boise Airport. The project consists of 10,000 s.f. of remodeled living and office, and apparatus space and 4,337 s.f. of new equipment storage and work space, including a 3400 s.f. apparatus bay housing two fire-fighting vehicles. Approximately 3500 s.f. of existing vehicle bay and storge space will remain. Existing exterior finishes will be removed and replaced with new insulated metal panel siding and cmu wainscot. Project includes a partial TPO reroof of the existing building including additional roof insulation, as well as new TPO roofing for the addition. Project shall comply with the 2012 International Green Construction Code as adopted by City of Boise. This building is fully fire sprinklered and alarmed. Any alterations to the sprinkler system shall comply with NFPA 13 and 72 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/5/201912/6/201912/6/2019APASS
DetailsJim Storey
Inspection requested via web by Ron Goff
FIRE-Final Inspection12/5/201912/5/201912/5/2019PPASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Alarm Testing12/5/201912/5/201912/5/2019PCANC
DetailsTroy Cobbley
wrong inspection type scheduled.

life safety reinspection Phone #: ###-#### Inspection requested via web by Ron Goff
BLD-Final2/14/20192/15/20192/15/2019PPART
DetailsBrandon Shaw
Temp. Occupancy for Phase 3 is approved...
FIRE-Final Inspection2/15/20192/15/20192/15/2019PPART
DetailsJim Page
Life fire safety inspection for Phase 3 complete. Will need to have access control comply with chapter 10 of IFC before final inspection of project.

Please call when at the gate Phone #: ###-#### Inspection requested via web by Harvey VanderVeen
FIRE-Final Inspection2/14/20192/15/20192/15/2019ACANC
DetailsJim Page
Please call when at the gate. Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/26/201810/26/201810/26/2018PPART
DetailsTroy Cobbley
Life safety for phase 2 passed
BLD-Final10/24/201810/25/201810/25/2018PPASS
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### Inspection requested via web by Harvey VanderVeen first phase ok
FIRE-Final Inspection10/24/201810/25/201810/25/2018PFAIL
DetailsTroy Cobbley
Need small documents, need exit discharge lighting corrected as discussed, need fire alrm permit and fire sprinkler work completed.


Temp. Occupancy for Phase 2 Phone #: ###-#### Inspection requested via web by Harvey VanderVeen
FIRE-Alarm Testing10/24/201810/25/201810/24/2018ACANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/24/201810/25/201810/24/2018ACANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
BLD-Final10/24/201810/25/201810/24/2018ACANC
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/23/201810/24/201810/24/2018PCANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Alarm Testing10/23/201810/24/201810/24/2018PCANC
DetailsTroy Cobbley
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
BLD-Final10/23/201810/24/201810/24/2018PCANC
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
BLD-Final10/19/201810/23/201810/19/2018ACANC
DetailsJim Storey
Temp. Occupancy for Phase 2 Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
FIRE-Final Inspection10/19/201810/22/201810/19/2018ACANC
DetailsTroy Cobbley
Phone #: ###-#### >> Inspection requested via web by Harvey VanderVeen Inspection cancelled from web by: Harvey VanderVeen
BLD-Final10/18/201810/19/201810/19/2018PNR
DetailsJim Sly
Temporary Occupancy for Phase 2. Early afternoon if possible Thanks Phone #: ###-#### Inspection requested via web by Harvey VanderVeen
Need Fire Final 1st.