Permit Information
Permit NumberBLD17-01763
StatusFinaled
Name ESI
Site Address 1219 S BROADWAY AVE
Project NameAlbertsons
Customer Number 
ePlanReviewYes
Description
(Albertsons/Market Street Idaho) **(Project Management- Ron Hill**) (PLAN MODIFICATION FOR EXTERIOR AND INTERIOR NOSTRUCTURAL MODIFICATIONS PRIMARY FO COSMETIC CHAGES TO THE PLANS) Permit for the construction of a new 64,621 sq. ft. Albertsons Grocery Store with work to include general site with utilities and the construction of the new building Per the approved plans. This is a fully fire sprinklered building for area increase. Demolition of current building with construction of new store and related site work.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/9/20191/10/20191/10/2019APASS
DetailsJim Storey
Please call 30 minutes prior to your site arrival. Phone #: ###-#### Inspection requested via web by Mike Beeson final ok grd permit final ok also grd17-00015
BLD-Final1/4/20191/8/20191/8/2019PCANC
DetailsJim Storey
Please call 30 minutes prior to arrival, if possible. Phone #: ###-#### >> Inspection requested via web by Mike Beeson Inspection cancelled from web by: Mike Beeson
BLD-Aging Inspection12/20/201812/20/201812/20/2018 PASS
DetailsJim Storey

Expires: 01/14/19
BLD-Aging Inspection10/11/201810/11/201810/11/2018 PASS
DetailsJim Storey
back ramp railling installed and passed// finals ok pending zoning
BLD-Conference8/11/20188/13/20188/13/2018APASS
DetailsJim Storey
Safety complaint on railings on eastern and northern side of upstairs patio not properly secured. rail apears to be fine one anchor bolt nut not tight to floor but is located at wall mount not needed for support.
BLD-Final7/16/20187/17/20187/17/2018APASS
DetailsJim Storey
Please call Roger when onsite. thanks
Phone #: ###-#### Inspection requested via web by Roger Wilson final ok pending rail on ramp back of store.
BLD-Framing/Rough-in7/12/20187/12/20187/12/2018APART
DetailsJim Storey
This is for the Broadway Shops wall. Phone #: ###-#### Inspection requested via web by Roger Wilson wrong permit// studs upside down
FIRE-Final Inspection7/10/20187/10/20187/10/2018APASS
DetailsJim Page
Previously noted items have been completed. Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers are in place with current inspection tags, hood fire suppression system inspections complete. Final life fire safety inspection complete.

Please call Roger Wilson or Mike Beeson when onsite Phone #: ###-#### Inspection requested via web by Roger Wilson
BLD-Final7/10/20187/10/20187/10/2018APART
DetailsJim Storey
Please call Roger Wilson when onsite. Thank you Phone #: ###-#### Inspection requested via web by Roger Wilson ramp and stairs handrails/ for temp/ insulation 2nd floor office at roof trastion.
FIRE-Final Inspection7/2/20187/3/20187/3/2018AFAIL
DetailsJim Page
Fire alarm permit FIR18-00124 needs to be finaled before life fire safety can be performed.

Fire finals Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Conference6/26/20186/26/20186/26/2018APASS
DetailsJim Storey
riecieved si close out letter sent to plan review.
BLD-Conference6/14/20186/15/20186/15/2018PPEND
DetailsDave Hannah
Deli area of discussion Phone #: ###-#### Inspection requested via web by Mike Beeson ok to bring in staff to train
FIRE-Final Inspection6/14/20186/15/20186/15/2018APART
DetailsJim Page
Partial life fire safety inspection is complete, fire sprinkler inspection is complete, fire alarm inspection is partially complete (see fire alarm comments under FIR18-00124), fire extinguishers are in place with current inspection tags, knox boxes are located by the main east entrance and another on the west side of the building.



Items that need to be corrected before final C of O, install emergency egress lighting and interior emergency lighting as discussed and marked on city approved drawings, rotate fire hydrant to correct orientation, provide documentation for testing of refrigerant detection system and alarm.


TCO for life fire safety authorized per conversation with Adele for EMPLOYEE TRAINING ONLY, all fire sprinkler systems and fire alarm system to remain active after this inspection.
FIRE-Conference6/14/20186/14/20186/14/2018PDONE
DetailsJim Page
Fire conference complete.

Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Ceiling Grid Inspection6/1/20186/4/20186/4/2018APASS
DetailsJim Storey
Deli area Phone #: ###-#### Inspection requested via web by Mike Beeson ceilling ok to cover// storage rm gyp ok
BLD-Ceiling Grid Inspection5/31/20185/31/20185/31/2018PPART
DetailsJim Storey
Front of deli Phone #: ###-#### Inspection requested via web by Mike Beeson ok need access to greese duct clean out.
FIRE-Sprinkler Rough-in5/31/20185/31/20185/31/2018PPART
DetailsJim Page
Installation of heat trace for fire sprinkler protection piping has been witnessed, heat trace installed on fire sprinkler piping for the exterior canopy on level 2 of the northeast side approved for cover.

Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Ceiling Grid Inspection5/29/20185/29/20185/29/2018PPASS
DetailsDave Hannah
Meat and bakery grid ceilings Phone #: ###-#### Inspection requested via web by Mike Beeson
FIRE-Conference5/29/20185/29/20185/29/2018PDONE
DetailsJim Page
Fire conference complete, a 24 hour fire watch will be required due to added fuel load from shelves being stocked, once fire sprinklers and fire alarm monitoring are complete and active then 24 hour fire watch will not be required.

Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Ceiling Grid Inspection5/14/20185/15/20185/15/2018APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson pharm/backery/offices ok to cover pending ele aprovals
BLD-Conference5/7/20185/8/20185/8/2018APASS
DetailsJim Storey
Need to meet and discuss the requirements for a temp C of O. Phone #: ###-#### Inspection requested via web by Roger Wilson
BLD-Footing5/1/20185/2/20185/2/2018APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson//ne sound wall ft and trellis pad ft ok to cover.
BLD-Framing/Rough-in5/2/20185/2/20185/2/2018APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson// flower shop and cooller as well as storage/office framing ok to cover located front of store.
BLD-Framing/Rough-in5/1/20185/1/20185/1/2018PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson pony wall at entry interior ok
BLD-Footing4/30/20185/1/20185/1/2018ACANC
DetailsJim Storey
Early am inspection if possible. Phone #: ###-#### >> Inspection requested via web by Roger Wilson Inspection cancelled from web by: Roger Wilson
BLD-Footing4/30/20184/30/20184/30/2018PCANC
DetailsJim Storey
Phone #: ###-#### >> Inspection requested via web by Roger Wilson Inspection cancelled from web by: Roger Wilson
BLD-Energy code compliance4/24/20184/24/20184/24/2018PPART
DetailsDave Hannah
Steve Condon is the contact person on site today. Phone #: ###-#### Inspection requested via web by Roger Wilson front wall of bluilding ok to cover int
BLD-Framing/Rough-in4/19/20184/19/20184/19/2018PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson soffits braced a d framing ok
BLD-Energy code compliance4/11/20184/12/20184/12/2018APART
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson pend ing arch submital
BLD-Framing/Rough-in4/11/20184/12/20184/12/2018APART
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson c/n 1009.9.3 Enclosures under interior stairways.
The walls and soffits within enclosed usable spaces under enclosed and unenclosed stairways shall be protected by 1-hour fire-resistance-rated construction or the fire-resistance rating of the stairway enclosure, whichever is greater. Access to the enclosed space shall not be directly from within the stair enclosure.// provide envalope w aplacation on how to insulate cooller and areas with no access
BLD-Framing/Rough-in4/3/20184/4/20184/4/2018APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson cooller walls/bakery and north stair all ok to cover. missed engenry code insulation walls.
BLD-Energy code compliance3/19/20183/20/20183/20/2018APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson south wall and se walls ok to cover
BLD-Framing/Rough-in3/15/20183/16/20183/16/2018APASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Roger Wilson wall and fur out ok to insulate south end of building.
BLD-Framing/Rough-in3/1/20183/2/20183/2/2018APASS
DetailsJim Storey
Roger Phone #: ###-#### west end mez ok to cover/ restrooms/emp area
BLD-Other10/12/201710/13/201710/13/2017APASS
DetailsJim Storey
Neighbors concerned that Grant st. setbacks are not correct. Verify west side setback along Grant street is correct. off sets placed by land survey engineer co.
BLD-Footing10/6/201710/9/201710/9/2017APART
DetailsJim Storey
First inspection for the footings. Concrete is scheduled for 12:00 pm. Thanks Phone #: ###-#### Inspection requested via web by Roger Wilson teracon si pending report. west/north corner ft wip ok