BLD-Final | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Ok for temp oc. Will be ok for perm occ. once zoning signs perm. No card on site to sign.
|
BLD-Final | 7/9/2018 | 7/9/2018 | 7/9/2018 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by David Scaggs Inspection cancelled from web by: David Scaggs
|
BLD-Final | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Noted some 20 min doors not installed, all 20 min doors need to be self closing. Fire caulk all penetrations in garages. Still need to verifiy 1 hr. wall continuity in garage to bottom of roof deck.
|
BLD-Final | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Needs mech. final.
|
FIRE-Final Inspection | 6/28/2018 | 6/28/2018 | 6/28/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Energy code compliance | 4/12/2018 | 4/12/2018 | 4/12/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Energy code compliance | 4/11/2018 | 4/11/2018 | 4/11/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Framing/Rough-in | 4/10/2018 | 4/10/2018 | 4/10/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs. Provide revised truss engineering, fireblock double common walls at 2nd. floor.
|
BLD-Framing/Rough-in | 4/9/2018 | 4/9/2018 | 4/9/2018 | P | NR |
Mike Jordan
|
|
|
Pending fire sprinkler inspection Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Wall Bracing | 3/29/2018 | 3/29/2018 | 3/29/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Wall Bracing | 3/28/2018 | 3/28/2018 | 3/28/2018 | P | NR |
Dave Hannah
|
|
|
Will have approved set of plans onsite. Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Wall Bracing | 3/27/2018 | 3/27/2018 | 3/27/2018 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by David Scaggs
|
BLD-Footing | 2/15/2018 | 2/15/2018 | 2/15/2018 | A | PASS |
Mike Jordan
|
|
|
Interior footings, concrete is scheduled for 9am Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 2/2/2018 | 2/2/2018 | 2/2/2018 | P | DEFR |
Mike Jordan
|
|
|
Interior footings, concrete is scheduled for 1pm Phone #: ###-#### Inspection requested via web by Marty Short. Concrete already placed when on site.
|
BLD-Energy code compliance | 1/24/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Mike Jordan
|
|
|
Foundation insulation Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Foundation | 1/22/2018 | 1/22/2018 | 1/22/2018 | P | PASS |
Mike Jordan
|
|
|
Concrete is scheduled for 2pm Phone #: ###-#### Inspection requested via web by Marty Short
|
BLD-Footing | 1/12/2018 | 1/12/2018 | 1/12/2018 | A | PASS |
Mike Jordan
|
|
|
Concrete scheduled for 10am Phone #: ###-#### Inspection requested via web by Marty Short
|