Permit Information
Permit NumberBLD18-00157
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameC30616 B37 Office Building
Customer Number 
ePlanReviewYes
Description
(MICRON B37 OFFICE BUILDING) ""PLAN MODIFICATION FOR UNDERGOUND PLUNBING AND STRUCTURAL MODIFICATIONS"" SCOPE:UNDERGROUND POWER SERVICE, UNDERSLAB PLUMBING, FOOTINGS, FOUNDATIONS, STEEL SUPERSTRUCTURE AND ELEVATED SLABS FOR B37 OFFICE BUILDING. Special inspections are required per the attached form 310. Grading under GRD17-00087. New Administrative Office Building, 3 - story's of approximately 53,500sf. each, this permit is to include the following. No occupancy under this permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled1/9/20191/9/20191/9/2019APASS
DetailsJim Storey
BLD-Ceiling Grid Inspection12/21/201812/21/201812/21/2018PCANC
DetailsJim Storey
1st floor Area A Phone #: ###-#### Inspection requested via web by Robert Snow
BLD-Final12/10/201812/14/201812/14/2018ACANC
DetailsMike Jordan
Dave Phone #: ###-####. Moved to pm.
BLD-Final12/12/201812/13/201812/13/2018ANR
DetailsMike Jordan
Dave Phone #: ###-####. Needs fire/life/safety TCO first. Needs exiting completed.
BLD-Framing/Rough-in8/17/20188/17/20188/17/2018PPASS
DetailsJim Storey
c/n 6/22 all idems made ok
BLD-Framing/Rough-in7/25/20187/26/20187/26/2018ANR
DetailsJim Storey
exterior walls and interrior // Dave Phone #: ###-####
BLD-Other6/6/20186/7/20186/7/2018PPASS
DetailsJim Storey
slab on grad // dave Phone #: ###-#### barrior in place rebar ok//
BLD-Framing/Rough-in5/31/20186/1/20186/1/2018APART
DetailsJim Storey
Dave Phone #: ###-#### work in progress/ need iecc at foundation r 10 and exterior insulation was propose due to lack of submitals on permit set.
BLD-Footing5/22/20185/24/20185/24/2018PPASS
DetailsJim Storey
Rebar/slab - Dave Phone #: ###-#### placed with si
BLD-Foundation5/9/20185/10/20185/10/2018PPASS
DetailsJim Storey
Kevin Phone #: ###-####sog ok
BLD-Concrete5/7/20185/8/20185/8/2018PFAIL
DetailsJim Storey
Dave Phone #: ###-#### k bracing lower bolt/nut needs tourqe test before concrete placment 4 locations// doug fir backing must be fire treated for this type of const.
BLD-Foundation5/7/20185/7/20185/7/2018PPASS
DetailsJim Storey
Dave-concrete reinforcement 2nd floor area C Phone #: ###-#### level 3 pass
BLD-Concrete5/2/20185/3/20185/3/2018PPASS
DetailsJim Storey
Dave Phone #: ###-####sog vappor barrior ok
BLD-Concrete5/2/20185/2/20185/2/2018PPASS
DetailsJim Storey
Dave Phone #: ###-#### slab on grade area 1 vappor barrior in place rebar spacing ok
BLD-Other4/18/20184/19/20184/19/2018PPASS
DetailsJim Storey
Area B level 2 slab on deck reinforcement // Kevin Honeycutt Phone #: ###-#### si to pick up missing deck welds se opening/east side.
BLD-Foundation4/17/20184/18/20184/18/2018PPASS
DetailsJim Storey
rebar for 3rd floor // Dave Phone #: ###-####
BLD-Concrete4/11/20184/11/20184/11/2018PPART
DetailsJim Storey
Area A level 2 SOMD reinforcing. Special inspector onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt si pick up west stair weld stuns missing/ clean up deck.
BLD-Concrete4/9/20184/10/20184/10/2018APASS
DetailsJim Storey
Level 3 SOMD reinforcement. Special Inspector to be onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt west end
BLD-Footing3/21/20183/22/20183/22/2018APASS
DetailsJim Storey
Elevator pits footings. Concrete at 10AM Geotek onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
BLD-Foundation2/28/20183/1/20183/1/2018APASS
DetailsJim Storey
GL-A,5 stem walls. GL-2 continuous footings. Concrete at 1PM, special inspector onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
BLD-Footing2/27/20182/28/20182/28/2018PCANC
DetailsJim Storey
Continuous footing GL-2. Stem walls GL-A,5. Concrete at 2PM special inspector onsite Phone #: ###-#### >> Inspection requested via web by Kevin Honeycutt
BLD-Footing2/26/20182/27/20182/27/2018APASS
DetailsJim Storey
Continuous footing GL-5,A,2. Special inspector onsite, Concrete is at 2PM ready for City inspection at 1PM. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
BLD-Footing2/26/20182/27/20182/26/2018PCANC
DetailsJim Storey
Continuous footing GL - A,5,2 Phone #: ###-#### >> Inspection requested via web by Kevin Honeycutt Inspection cancelled from web by: Kevin Honeycutt
BLD-Footing2/21/20182/21/20182/22/2018PPEND
DetailsDave Hannah
Spread footings GL- B;C/ GL-3;4. Special Inspector onsite Phone #: ###-#### Inspection requested via web by Kevin Honeycutt ok after spec sign offs
BLD-Footing2/20/20182/20/20182/20/2018PPART
DetailsJim Sly
Ready at 3:30 PM. Concrete tomorrow at 4:30 AM. Special inspector will be onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
Matt footings and piers at Gridline A, 5 and 2. OK pending Geotek special inspection, tests and approvals.
BLD-Foundation2/14/20182/15/20182/15/2018PPASS
DetailsJim Storey
Mat footing on GL-2 between J;K. Stem walls on GL-2 between D;H. Stem walls on GL-5 between F;L. Stem walls on GL-4 between L;N. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
BLD-Footing2/12/20182/13/20182/13/2018APASS
DetailsJim Storey
Continuous footing on GL-2 ; 5. Concrete is at 12PM, special inspector will be onsite. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt
BLD-Footing2/6/20182/7/20182/7/2018APART
DetailsJim Storey
Call if you have trouble finding us. Concrete is scheduled for 12PM, Special inspection is complete. Phone #: ###-#### Inspection requested via web by Kevin Honeycutt no aproved plan on site si on site/ genral confomance ok / engineers aproval on site review ok to place concrete