BLD-Final | 9/12/2018 | 9/12/2018 | 9/12/2018 | P | PASS |
Jim Storey
|
|
|
Call ahead for access - Laura (school director) Phone #: ###-####
|
BLD-Final | 8/30/2018 | 8/31/2018 | 8/31/2018 | P | PART |
Mike Jordan
|
|
|
Richard Phone #: ###-####. Ok for temp occ. Waiting on tempered glazing to be installed.
|
FIRE-Final Inspection | 8/30/2018 | 8/31/2018 | 8/31/2018 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
Richard Phone #: ###-####
|
FIRE-Conference | 8/29/2018 | 8/29/2018 | 8/29/2018 | P | DONE |
Troy Cobbley
|
|
|
We spoke of fire extinguisher placement, the removal of the shrubs obstructing the FDC, placement of the outside alarm bell at the FDC, and placement of the knox key box. We also discussed removing the ceiling T-bar wireing from the sprinkler piping.
|
BLD-Ceiling Grid Inspection | 8/24/2018 | 8/24/2018 | 8/24/2018 | P | PASS |
Jim Storey
|
|
|
Richard Phone #: ###-#### ceilling ok pending mech aproval
|
BLD-Conference | 8/16/2018 | 8/16/2018 | 8/16/2018 | P | DONE |
Bob Archibald
|
|
|
Met with contractor and discussed requirements for temp/final occupancy. required signatures, life safety provisions, etc..
|
BLD-Framing/Rough-in | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Jim Storey
|
|
|
Richard Phone #: ###-####
|