Information based on query as of Friday, May 10, 2024.
Permit Information
Permit NumberBLD18-01246
StatusFinaled
Name OKLAND CONSTRUCTION CO INC
Site Address 1290 W MYRTLE ST
Project NamePioneer Crossing Office Buildi
Customer Number 
ePlanReviewYes
Description
(PIONEER CROSSING OFFICE BUILDING) ""PLAN MODIFICATION TO CHANGE THE EXTERIOR FINISH OF THE SOUTH STAIR TOWER"" Permit for the buildout of the core and shell with work to include, restrooms, elevators, entry lobby, electrical, mechanical and fire sprinkler systems per the approved plans. This is a fully sprinklered and alarmed building for area and height increase. The building is type IIB over a type 1A podium per the special provisions of section 510.2/2015 IBC. This permit does not include utilities, foundation or superstructure. This building is fully fire sprinklered for height and area increase Please reference permit BLD18-01166. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection8/7/20198/8/20198/8/2019PPASS
DetailsJim Page
Remaining item for radio coverage complete, final life fire safety inspection complete.

Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Final6/4/20196/7/20196/7/2019PPASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Sam Reading
FIRE-Final Inspection6/4/20196/6/20196/6/2019PPART
DetailsJim Page
Final life fire safety inspection for core and shell substantially complete. Radio test for fire department radio coverage did not pass. A TCO is authorized per conversation with Ron Johnson with Boise Fire contingent on radio coverage issue being resloved, all other items for life fire safety have been inspected and passed.

Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Ceiling Grid Inspection5/10/20195/13/20195/13/2019PPASS
DetailsDave Hannah
Level 3 Ceiling Grid. Phone #: ###-#### Inspection requested via web by Sam Reading 4th fl also ok
BLD-Conference5/6/20195/8/20195/8/2019ADONE
DetailsDave Hannah
Conference to discuss Beneficial Occupancy for the Core and Shell. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Ceiling Grid Inspection4/30/20195/1/20195/1/2019PPASS
DetailsDave Hannah
Level 2 Grid. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Ceiling Grid Inspection4/23/20194/24/20194/24/2019APART
DetailsDave Hannah
L1 Ceiling grid Phone #: ###-#### Inspection requested via web by Sam Reading needs elec r/i and also needs mec to strape defusers
BLD-Framing/Rough-in3/1/20193/4/20193/5/2019PPART
DetailsDave Hannah
Sam Phone #: ###-#### core elev and rest rooms ok 5th floor
BLD-Framing/Rough-in2/27/20192/27/20192/27/2019PPASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Framing/Rough-in2/25/20192/26/20192/26/2019APEND
DetailsJim Sly
Stairwell lids and level 5 shaft and core. Phone #: ###-#### Inspection requested via web by Sam Reading Complete Firestopping at Stairwell Rated Walls, Check HVAC shaft termination at roof deck.......Beams?? Per approved plan? Complete fire stopping of penitrations....Inside.
BLD-Wall cover2/6/20192/7/20192/7/2019APASS
DetailsDave Hannah
North stair tower, Levels 3 and 4 lids Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Wall cover2/4/20192/5/20192/5/2019PCANC
DetailsDave Hannah
North stairwell and level 3 ceilings Phone #: ###-#### >> Inspection requested via web by Sam Reading Inspection cancelled from web by: Sam Reading
BLD-Wall cover1/24/20191/25/20191/25/2019APASS
DetailsDave Hannah
South stair tower insulation. 2nd floor 2 siding drywall. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Wall cover1/23/20191/24/20191/24/2019PDEFR
DetailsJim Storey
South stair tower insulation. 2nd floor 2 siding drywall. Phone #: ###-#### Inspection requested via web by Sam Reading out of time
BLD-Wall cover1/14/20191/15/20191/16/2019PCANC
DetailsDave Hannah
1st floor insulation for 2 siding drywall. Phone #: ###-#### Inspection requested via web by Sam Reading core areas restrooms elev lobby ok
BLD-Wall cover1/2/20191/2/20191/2/2019PPART
DetailsDave Hannah
Contact Sam Reading. 1st floor interior framing and shaft wall framing at elevators 1-5. Phone #: ###-#### Inspection requested via web by Sam Reading
BLD-Framing/Rough-in11/14/201811/14/201811/15/2018PPART
DetailsDave Hannah
Steve Phone #: ###-####
BLD-Framing/Rough-in11/1/201811/2/201811/2/2018APART
DetailsDave Hannah
Steve Phone #: ###-#### ext sofit and wall 1rst 2nd 3rd floors
BLD-Framing/Rough-in9/21/20189/24/20189/24/2018APART
DetailsDave Hannah
Steve Phone #: ###-#### ext framing okwest half first floor
BLD-Conference3/21/20193/21/2019 P 
DetailsDave Hannah
Discussion on additional corridors affecting Certificate of Occupancy date. Phone #: ###-#### >> Inspection requested via web by Sam Reading