BLD-Energy code compliance | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Frazier,, under floor and attic ok
|
DOC - Permit Finaled | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Tony Young
|
|
|
c of c /o issued
|
BLD-Final | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Wall cover | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | PASS |
Jim Sly
|
|
|
Ready Friday afternoon Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Framing/Rough-in | 7/27/2018 | 7/30/2018 | 7/30/2018 | A | PASS |
Jim Sly
|
|
|
Ready for Friday Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Energy code compliance | 7/25/2018 | 7/27/2018 | 7/30/2018 | P | PASS |
Jim Sly
|
|
|
And permission to cover. Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Framing/Rough-in | 7/25/2018 | 7/26/2018 | 7/26/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Frazier Need Plumb. and Electr. Rough In Approvals
|
BLD-Other | 7/26/2018 | 7/26/2018 | 7/26/2018 | P | PASS |
Jim Sly
|
|
|
Sheer inspection in light of conversation this morning Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Energy code compliance | 7/23/2018 | 7/26/2018 | 7/25/2018 | A | CANC |
Jim Sly
|
|
|
Phone #: ###-#### >> Inspection requested via web by Robert Frazier Inspection cancelled from web by: Robert Frazier
|
BLD-Framing/Rough-in | 7/22/2018 | 7/24/2018 | 7/23/2018 | P | CANC |
Jim Sly
|
|
|
Rough-in for addition framing Phone #: ###-#### >> Inspection requested via web by Robert Frazier Inspection cancelled from web by: Robert Frazier
|
BLD-Framing/Rough-in | 7/12/2018 | 7/13/2018 | 7/13/2018 | P | NR |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Frazier Need Electr R/I
|
BLD-Conference | 7/12/2018 | 7/12/2018 | 7/12/2018 | P | DONE |
Jim Sly
|
|
|
Talk through permission to cover Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Wall cover | 7/2/2018 | 7/3/2018 | 7/3/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Framing/Rough-in | 7/3/2018 | 7/3/2018 | 7/3/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Frazier.. New double level beam ok in existing structure in place of demoed bearing wall.
|
BLD-Conference | 7/2/2018 | 7/2/2018 | 7/2/2018 | P | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Robert Frazier
|
BLD-Foundation | 6/18/2018 | 6/19/2018 | 6/19/2018 | A | PASS |
Mike Jordan
|
|
|
Robert-stem wall-pour time 11:15 Phone #: ###-####
|
BLD-Footing | 6/15/2018 | 6/18/2018 | 6/18/2018 | A | PASS |
Mike Jordan
|
|
|
Robert Phone #: ###-####. set backs ok.
|
BLD-Footing | 6/13/2018 | 6/15/2018 | 6/15/2018 | P | PART |
Jim Sly
|
|
|
Robert Phone #: ###-#### Looks OK ....No plans. Called Contractor, He says plans show measurement from street, and he said it matches plan. Told him to pour at own risk.
|