Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberBLD18-02006
StatusFinaled
Name SHADOW MOUNTAIN CONST INC
Site Address 4018 N SANDPOINT WAY
Project NameTivoli
Customer Number 
ePlanReviewYes
Description
***Prescriptive component energy approach*** WUI ZONE A REQUIREMENTS*** Permit for the construction of a new 3,075 sq. ft., one story single family dwelling with 4 bedrooms, 3 and a half bathrooms, approximately 352 sq. ft. of covered patio/porch and a 1,066-sq. ft. attached garage per the approved plans and any notations. A-1 zoning and setbacks per planning. MDH

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/24/20196/24/20196/24/2019PPASS
DetailsTony Young
DOC - Permit Finaled6/24/20196/24/20196/24/2019PPASS
DetailsTony Young
BLD-Final6/21/20196/24/20196/24/2019ADONE
DetailsTony Young
Scott Phone #: ###-####-call for access
BLD-Blower Door Test Results6/24/20196/24/20196/24/2019PDONE
DetailsTony Young
Scott Phone #: ###-####-call for access// 3.9
BLD-Final6/20/20196/21/20196/21/2019APEND
DetailsTony Young
Scott Phone #: ###-####-call for access,, needs hillside,, then ok
BLD-Other11/13/201811/14/201811/14/2018APART
DetailsTony Young
Sofit // Sott Phone #: ###-####,, work in progress,, ok
BLD-Energy code compliance11/8/201811/9/201811/9/2018APASS
DetailsMike Jordan
Scott Phone #: ###-####
BLD-Framing/Rough-in11/2/201811/5/201811/5/2018PPASS
DetailsTony Young
Scott Phone #: ###-####
BLD-Wall Bracing10/17/201810/17/201810/17/2018PPASS
DetailsTony Young
exterior shear // scott johnson Phone #: ###-####
BLD-Footing8/24/20188/24/20188/24/2018PPASS
DetailsTony Young
pat