Information based on query as of Wednesday, May 1, 2024.
Permit Information
Permit NumberBLD18-03143
StatusTemporary Occupancy
Name ESI
Site Address 502 W FRONT ST
Project NameHomes 2 Suites by Hilton
Customer NumberBLD18-01831 GARAGE
ePlanReviewYes
Description
**Partial TCO** HOME 2 SUITES BY HILTON – FRONT STREET DEVELOPMENT – HOTEL PHASE AND GARAGE TI) (DRH17-00530) (5-24-19 PLAN MODIFICATION) (4-2-19 PLAN MODIFICATION.) The fire sprinkler system is used for fire flow and for occupancy and is required throughout the entire building, including the open parking garage. To construct the hotel phase of a multi-phase project and to complete the tenant improvement phase of the parking garage. This permit is intended to establish a Certificate of Occupancy for the entire building. This building will be 7 stories tall and will have 7 levels of parking. Site grading and site work was done under permit GRD18-00041. The concrete garage superstructure phase was done under permit BLD18-01831. The total floor area of the hotel will be about 92,692 square feet (13,732 square feet 1st story, 13,160 square feet 2nd story, 13,160 square feet 3rd story, 13,160 square feet 4th story, 13,160 square feet 5th story, 13,160 square feet 6th story, and 13,160 square feet 7th story). The total area of the building is about 289,099 square feet (45,151 square feet 1st story, 43,769 square feet 2nd story, 43,769 square feet 3rd story, 43,769 square feet 4th story, 43,769 square feet 5th story, 43,769 square feet 6th story, and 25,103 square feet 7th story). There will be a total of 138 hotel sleeping units. A total of 7 hotel sleeping units are required to be accessible to the disabled. Two or more of the required accessible units are required to have accessible roll-in type showers. The remaining required accessible units are allowed to have accessible bathtubs. Above the 1st story of the hotel, the hotel is required to be separated from the open parking garage by a 2-hr fire-resistance-rated fire barrier wall that functions as a shaft wall. The fire barrier wall is required to create a complete separation and to extend from the floor between the 1st and 2nd story of the hotel all the way to the underside of the top floor of the parking garage. Work is to include a few steel columns with steel baseplates, steel beams, steel stud bearing walls with base plates attached to concrete floors with powder actuated fasteners, floors constructed of steel joists and steel floor decking, 3” concrete floor slabs with drag bars placed on top of steel floor decking, steel roof joists with steel roof decks, continuous roof insulation installed on top of steel roof decks with a membrane roof covering above, roof top glass “beacon” structure, mechanical unit screens, roof hatch and alternating tread device for roof access, 2-hr stairway enclosures, 2-hr elevator shaft with a concrete pit, 24” diameter laundry chute within a 2-hr shaft having 90 minute self-closing access doors, 2-hr laundry chute termination room, 2-hr mechanical shafts, 2-hr exhaust shafts, 1-hr laundry chute access rooms with 45 minute doors, 1-hr corridors with 20 minute smoke- and draft-control assemblies, exterior fixed windows, aluminum storefront windows and doors, interior doors, metal siding, EIFS, wood siding, brick veneer, stone veneer with stone window sill caps, suspended acoustical ceilings, suspended gypsum board ceilings and soffits, a direct vent duel sided gas fireplace, millwork, and interior finishes. Special Inspection is required for steel (including welding and bolting), post-installed anchors in hardened concrete, and EIFS. Each hotel sleeping room will be served by its own VTAC unit and exhaust duct. The swimming pool is required to be done under a separate permit. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Ceiling Grid Inspection8/5/20208/6/20208/6/2020APASS
DetailsDave Hannah
Level 3 and Level 4 Corridors. Call Adam When heading to site.

Thanks. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection7/23/20207/27/20207/28/2020PPART
DetailsDave Hannah
Coordinate visit with Mike Beeson, Adam off site. Level 2 and level 3 ceiling inspections for cover. Phone #: ###-#### Inspection requested via web by Adam Johnson 2nd fl ok
BLD-Wall cover7/23/20207/23/20207/23/2020PPASS
DetailsDave Hannah
Shafts and other. Call Adam when heading over. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in7/21/20207/21/20207/21/2020PCANC
DetailsMike Jordan
Firestop assemblies, SE Shaft. Other areas outlined between Forte and ESI. Call adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection7/21/20207/21/20207/21/2020APASS
DetailsMike Jordan
First floor fat grid framing, and back of house ceiling grid cover inspection Phone #: ###-#### Inspection requested via web by Mike Beeson.. 1st floor hardlid in lobby and eatry ok. back of house not ready.
BLD-Framing/Rough-in7/16/20207/16/20207/16/2020APASS
DetailsDave Hannah
Level 6, Level 5, Level 4 Shaft Wall Framing at SE Mechanical Shaft. Call Adam to coordinate time and details for site visit. COVID Protocols in place to clear the areas before arrival. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover7/2/20207/6/20207/6/2020PPART
DetailsBrandon Shaw
East Shaft at level 7, level 6. Late PM if Possible. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in7/1/20207/1/20207/1/2020PPASS
DetailsDave Hannah
7th Floor, fire stop at ceilings, 6th Street Side. Call adam when heading to site. Will provide garage access. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover6/29/20206/30/20206/30/2020APART
DetailsDave Hannah
7th Floor Framing walk, FIrestop assemblies. Call Adam before heading to site. 30 min as discussed for Covid preparation. Phone #: ###-#### Inspection requested via web by Adam Johnson part south side rooms ok
BLD-Conference6/29/20206/29/20206/29/2020PDONE
DetailsDave Hannah
Conference in ESI office to discuss the following:
-FFE and Hotel Staging
-Overall Inspection Tracking
-Linen Chute at Level 7
ESI Crew will be masked while visiting in the field office. Please call Adam when heading this way. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in6/22/20206/23/20206/23/2020APASS
DetailsDave Hannah
2nd Floor Corridor at Stair tower. Additional items. list will be available, call Adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover6/16/20206/16/20206/16/2020PPASS
DetailsDave Hannah
Level 6 Secondary Framing. Call Adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in6/11/20206/11/20206/11/2020APART
DetailsDave Hannah
Fire Caulking at Level 6, 6th Street side. Call Adam when heading to site. Thanks AKJ ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover6/8/20206/9/20206/9/2020APEND
DetailsDave Hannah
Elevator lobby shafts on 2 , 5 and 6 Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Framing/Rough-in5/28/20206/1/20206/1/2020APASS
DetailsDave Hannah
Pool area cover/ 5th floor Fire assembly/fire caulking
Call Adam when heading to site. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover5/28/20205/29/20205/29/2020APASS
DetailsMike Jordan
Level 5 fur downs at rooms 6th. st. south only ok. Pool room exterior wall insulation ok, 1st. level.
BLD-Framing/Rough-in5/20/20205/21/20205/21/2020APASS
DetailsDave Hannah
Complete L4, front street side of bathroom assemblies at ceiling. Call Adam when heading to site. Thanks AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover5/11/20205/11/20205/11/2020APASS
DetailsDave Hannah
First floor and 7th floor insulation Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Framing/Rough-in5/6/20205/6/20205/7/2020PPART
DetailsDave Hannah
Level 3, 6th street rework of fire stops per yesterdays inspections. Call Adam when heading to site. AKJ ###-####. Phone #: ###-#### Inspection requested via web by Adam Johnson need enfo on 3inch pvc fire stopping and fix two spots on shafts plumbing interferace
BLD-Framing/Rough-in5/5/20205/5/20205/6/2020PPART
DetailsDave Hannah
Level 3 Fire Caulking, 6th street corridor. Call Adam when heading to site. Thanks AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in4/29/20204/30/20204/30/2020APASS
DetailsDave Hannah
Level 3 framing at 6th street cooridor. Firestop at soffit overbuilds. Call Adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Conference4/22/20204/22/20204/23/2020PPASS
DetailsDave Hannah
Inspection walk of hotel secondary framing, firestop assemblies, and other areas for cover. Final list generated, call Adam when heading to the site. AKJ ###-####
Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in4/16/20204/16/20204/16/2020PPASS
DetailsDave Hannah
2nd floor recheck of 2" tub drains in soffit framing. If possible, Level 5 Electrical Room at Mech Shaft. (Shaft wall assembly). Coordinate with Adam. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Energy code compliance4/15/20204/16/20204/16/2020APASS
DetailsDave Hannah
Ongoing cover inspections. List TBD at time of walk with Adam/ Mike. Call when heading to site. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover4/13/20204/13/20204/13/2020APASS
DetailsDave Hannah
Putty packs level 6 and secondary framing level 2. Call Adam before heading to site. Thanks. Akj. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover4/6/20204/7/20204/8/2020PPASS
DetailsDave Hannah
Walk Level 4 insulation, 6 insulation. Putty packs on L6. Look at MECH shafts, follow up to emailed pictures. Call Adam 30 minutes in advance to clear the inspection areas. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in4/1/20204/1/20204/1/2020PPART
DetailsDave Hannah
Level 5 Putty Packs. Verify install before insulation. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson ok to insulate 5th flr and reck hallway
BLD-Conference4/1/20204/1/20204/1/2020PPASS
DetailsDave Hannah
Revised TCO Plan - Rev 1.1, Level 7 Garage. Call Adam when heading to site. Thanks AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson ok for new tco
BLD-Conference3/30/20203/30/20203/31/2020PDONE
DetailsDave Hannah
Inspection walk. Adam Defining scope for todays walk. Call Adam when heading to site.

Putty Packs
Insulation
secondary Framing at bathrooms.
Thanks, AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in3/30/20203/30/20203/31/2020APART
DetailsDave Hannah
2nd floor shaft walls and insulation on Level 4 Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Wall cover3/25/20203/25/20203/26/2020PPASS
DetailsDave Hannah
Hotel, Level 3 insulation for cover. Level 4 putty packs, pre insulation. Thanks, AKJ. Call adam when heading to site. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Wall cover3/23/20203/23/20203/23/2020PPART
DetailsDave Hannah
Ongoing framing inspection. Walk items as they are ready for inspection. Call adam when heading to site. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson ok up to 411
BLD-Wall cover3/20/20203/20/20203/20/2020PPASS
DetailsDave Hannah
Hotel insulation, putty packs, close walls on L-3 Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Framing/Rough-in3/19/20203/19/20203/19/2020PPART
DetailsDave Hannah
Adam Phone #: ###-#### level 2 ok to cover level 3 ok to insulate
BLD-Framing/Rough-in3/17/20203/17/20203/18/2020PPART
DetailsDave Hannah
2nd Floor Framing, 224 down, putty pack verification, framing cover. Call Adam when heading to site. ###-####. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson 0k up to room 206
BLD-Final3/13/20203/16/20203/16/2020PPART
DetailsDave Hannah
Phase 1 TCO Final inspection walk.Call Adam to coordinate. ###-####. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for tco
FIRE-Final Inspection3/13/20203/16/20203/16/2020PPART
DetailsJim Page
Final life fire safety inspection for TCO phase 1 complete, signatures provided for associated trades on the Phase 1 TCO permit sign of card.

Fire final for Phase 1 TCO. Call Adam to coordinate. Thanks. AKJ Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in3/13/20203/16/20203/16/2020APART
DetailsDave Hannah
Level 2 West Room Inspections, putty packs installed. Ready for Cover. Call Adam when heading to site. AKJ ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson first 5 roomsup to 219 ok to cover
BLD-Framing/Rough-in3/13/20203/13/20203/13/2020APASS
DetailsDave Hannah
Level 3 and level 4 hotel framing at corridor for cover. Ongoing cover inspections. Call Adam when heading to site. Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in3/11/20203/11/20203/11/2020PNR
DetailsDave Hannah
Adam Phone #: ###-####
BLD-Wall cover3/6/20203/9/20203/10/2020PNR
DetailsDave Hannah
2nd floor cover in guestrooms and corridors, Corridors level 3-6 Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Final3/6/20203/6/20203/6/2020PCANC
DetailsBrandon Shaw
Phase 1 TCO final review and inspection walk for Fire Life Safety, Walk About. AM and PM slot reserved pending final Electrical and FLS walks respectively. akj

Call adam when heading to the site. ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Final3/6/20203/6/20203/6/2020ACANC
DetailsBrandon Shaw
Phase 1 TCO final review and inspection walk for Fire Life Safety, Walk About. AM and PM slot reserved pending final Electrical and FLS walks respectively. akj

Call adam when heading to the site. ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
FIRE-Final Inspection3/6/20203/6/20203/6/2020PFAIL
DetailsJim Page
Provide emergency egress public way lighting on nothwest stairwell at level 1 discharge as discussed. Provide proper freeze protection for dry pipe valve stairwell, southeast side. Install glass in fire rated doors from hotel section too garage. Dry system trip times for level 1 and 6 not met, no other dry systems were tested, sprinklers cannot be signed off for phase 1 until trip times are met. Inspection stopped due too defeciencies.



Phase 1 TCO final review and inspection walk for Fire Life Safety

Call adam when heading to the site. ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
FIRE-Conference3/6/20203/6/20203/6/2020ADONE
DetailsJim Page
Fire conference is complete, no generator transfer performed due to other defeciencies that stopped inspections.

Emergency lighting test of genset system with ESI and RME Crew. Preferably late morning, after 10:00 am.

Call adam when heading to the site. ###-#### Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Framing/Rough-in2/28/20203/2/20203/2/2020APASS
DetailsDave Hannah
First floor back of house cover inspection Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Framing/Rough-in2/18/20202/19/20202/19/2020APASS
DetailsDave Hannah
Roof framing Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Framing/Rough-in1/28/20201/28/20201/28/2020PPART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Mike Beeson soffits / hardlids garage ok to cover
BLD-Conference12/3/201912/4/201912/4/2019ADONE
DetailsTell Riley
Stairwell review Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Framing/Rough-in11/18/201911/18/201911/18/2019APASS
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Mike Beeson
BLD-Conference11/15/201911/15/201911/15/2019PDONE
DetailsDave Hannah
Adam Phone #: ###-####
BLD-Framing/Rough-in10/30/201910/30/201911/6/2019PPART
DetailsDave Hannah
Phone #: ###-#### Inspection requested via web by Mike Beeson 2nd and 3rd floor ok ground floor ok to cover top4ft of walls
BLD-Conference8/13/20208/14/2020 P 
DetailsDave Hannah
Adam Phone #: ###-####