BLD-Final | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 5/22/2019 | 5/22/2019 | 5/22/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.88
|
BLD-Energy code compliance | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Framing/Rough-in | 3/19/2019 | 3/19/2019 | 3/19/2019 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
BLD-Framing/Rough-in | 3/13/2019 | 3/14/2019 | 3/14/2019 | P | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon. Previously noted hardware not yet installed.
|
BLD-Framing/Rough-in | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PEND |
Brandon Shaw
|
|
|
Install CST strap per plans at tall wall, see framing pg... OK to insulate...
|
BLD-Wall Bracing | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending installation of remaining two hold downs and two anchor botls...
|
BLD-Wall Bracing | 2/22/2019 | 2/26/2019 | 2/26/2019 | P | FAIL |
Brandon Shaw
|
|
|
Hold downs to be installed correctly... Anchor bolts to be no more than 12" from ends of sill plates... Need a ledible Approved set of plans...
|
BLD-Framing/Rough-in | 2/22/2019 | 2/26/2019 | 2/26/2019 | P | CANC |
Brandon Shaw
|
|
|
Phone #: ###-#### >> Inspection requested via web by Gus Brandon Inspection cancelled from web by: Gus Brandon
|
BLD-Foundation | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 11/5/2018 | 11/5/2018 | 11/5/2018 | P | PASS |
Dave Hannah
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|