(FAIRVIEW APARTMENTS) (BLDG D3) (DRH17-00532) (GRD18-00035) Permit for the construction of Building D3, a 8,737 sq ft, 2-story, 8-unit apartment building. This building is one of six buildings within a multi-family development, which includes (3) three-story, 24-unit multi-family buildings and (3) two-story, 8-unit buildings for a total of 96 units on the site. Work to include general site work and the construction of the new building per the approved plans. Special inspections are required for post installed anchors into concrete when used per Sheet S-001.1 and Form 310. All buildings are to be fully fire sprinklered with an NFPA 13-R system as required for residential occupancy and story increase. **JAR**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/16/201910/16/201910/16/2019PPASS
DetailsTell Riley
PAT Phone #: ###-####//all trades passed and life safety//all signatures required complete//final complete//
BLD-Final10/14/201910/15/201910/15/2019PCANC
DetailsTell Riley
Pat Phone #: ###-####
FIRE-Final Inspection10/14/201910/15/201910/15/2019APASS
DetailsTroy Cobbley
Life safety passed. Phone #: ###-####
BLD-Aging Inspection9/16/20199/16/20199/16/2019 PASS
DetailsTell Riley
WIP....
BLD-Final7/16/20197/16/20197/16/2019PPASS
DetailsTell Riley
Bill Phone #: ###-####//corrections made//ok for temp occupancy//
BLD-Final7/10/20197/10/20197/10/2019PFAIL
DetailsTell Riley
Matt Phone #: ###-####//need to seal penetrations in storage rooms//label fire riser room//anchor railings at stairway//will call for re-isnpection//
BLD-Energy code compliance4/3/20194/4/20194/4/2019APASS
DetailsJim Sly
Bill Phone #: ###-####
BLD-Framing/Rough-in4/1/20194/1/20194/1/2019PPASS
DetailsJim Sly
Bill Phone #: ###-####
BLD-Wall Bracing3/19/20193/19/20193/19/2019PPASS
DetailsJim Sly
Bill Phone #: ###-####
BLD-Foundation1/16/20191/17/20191/17/2019PPASS
DetailsJim Storey
Dane Phone #: ###-####
BLD-Footing1/15/20191/16/20191/16/2019PPASS
DetailsJim Sly
Dean Phone #: ###-####
BLD-Footing1/14/20191/15/20191/16/2019PCANC
DetailsJim Sly