Permit Information
Permit NumberBLD18-03672
StatusIssued
Name RECORD STEEL AND CONSTRUCTION INC
Site Address 3550 N WINSOME PL
Project NameJohnson Residence
Customer Number 
ePlanReviewYes
Description
**HILLSIDE** **WUI FOOTHILLS** **SPECIAL INSPECTIONS** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 5155 sq. ft., two story (first story 3620 sq. ft., second story 1535 sq. ft.) single family dwelling with 4 bedrooms, 4.5 bathrooms, approximately 1380 sq. ft. of covered patio/porch and a 1771 sq. ft. attached garage per the approved plans and any notations. A-1DA zoning and setbacks per planning. An NFPA 13D sprinkler system is being provided, as noted on revised cover sheet. Radiant heating system being provided for driveway. JJNA letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.


All disturbed slopes included in the construction of this project must be stabilized and approved by Public Works before a Final Occupancy Permit is granted. If weather conditions prohibit revegetation and stabilization activities, the contractor shall provide a bond/surety agreement or an irrevocable letter of credit in the amount of 110% of the cost estimated by the project engineer to enable stabilization of the site. Call 208-608-7168 for an inspection. JJN
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection8/6/20208/6/20208/7/2020 PASS
DetailsTony Young
BLD-Framing/Rough-in3/24/20203/25/20203/25/2020APART
DetailsDave Hannah
The house has been approved plumbing and electrical. The HVAC has been approved for the second floor. The builder is requesting approval to apply gypboard to the second floor only. A follow on inspection will be scheduled for later next week? or when the fireplace chimney flue is installed. The delivery of the flue pipe has been delayed. Phone #: ###-#### Inspection requested via web by John Cloninger ok to cover second floor
BLD-Framing/Rough-in11/12/201911/13/201911/13/2019PPART
DetailsTony Young
Structural inspection prior to application of foam insulation. Third party inspection log on site. The roof deck will receive 8" of foam insulation on the underside. This inspection is to check to see if the City will approve the cover of the structural components for cover.The Electrical, Plumbing and Mechanical will be added after the insulation is installed. Phone #: ###-#### Inspection requested via web by John Cloninger/
top of floor/ceiling cavities ok to spray foam,, trades will be under,, structural engineer to inspect prior to foam..
BLD-Footing1/13/20191/14/20191/14/2019APEND
DetailsTony Young
Pouring caissons for grade beams to bear on. Continuous inspection will be provided by MTI and the pour time is noon. Phone #: ###-#### Inspection requested via web by John Cloninger,, ok pending special inspection report
BLD-Conference1/10/20191/10/20191/10/2019PPART
DetailsTony Young
piers ok per J Taylor,, pending special inspection report,, see his notes on this day
BLD-Footing1/9/20191/10/20191/10/2019AFAIL
DetailsBrandon Shaw
Need soil subgrade submitted and approved by PW before inspection can be completed...
BLD-Aging Inspection8/7/20208/7/2020   
DetailsTony Young