BLD-Final | 7/26/2019 | 7/26/2019 | 7/26/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Kellan Curtis
|
DOC - Permit Finaled | 7/26/2019 | 7/26/2019 | 7/26/2019 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 7/24/2019 | 7/26/2019 | 7/26/2019 | A | DEFR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kellan Curtis
|
BLD-Final | 7/15/2019 | 7/18/2019 | 7/18/2019 | A | NR |
Jim Storey
|
|
|
Kellan Phone #: ###-####
|
BLD-Conference | 6/24/2019 | 6/27/2019 | 6/27/2019 | A | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kellan Curtis,, walk through for final,, need trades,, zoning,, hand rails
|
BLD-Energy code compliance | 4/10/2019 | 4/12/2019 | 4/12/2019 | A | PASS |
Tony Young
|
|
|
Kellan Phone #: ###-####
|
BLD-Framing/Rough-in | 4/8/2019 | 4/8/2019 | 4/8/2019 | P | PART |
Tony Young
|
|
|
Kellan Phone #: ###-####,, seal pack,,work in progress,, ok to insulate
|
BLD-Framing/Rough-in | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | NH |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kellan Curtis// locked up
|
BLD-Framing/Rough-in | 3/28/2019 | 3/29/2019 | 3/29/2019 | A | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Kellan Curtis
|
BLD-Wall Bracing | 3/1/2019 | 3/4/2019 | 3/4/2019 | A | PASS |
Mike Jordan
|
|
|
Curtis Phone #: ###-####
|
BLD-Wall Bracing | 2/27/2019 | 3/1/2019 | 3/1/2019 | A | PART |
Tony Young
|
|
|
Curtis Phone #: ###-####,, ok to cover around windows,, need to re-do some areas
|
BLD-Conference | 1/27/2019 | 1/30/2019 | 1/30/2019 | P | DONE |
Brandon Shaw
|
|
|
Head hieght at stairs ok...
|
BLD-Foundation | 12/6/2018 | 12/6/2018 | 12/7/2018 | P | PART |
Tony Young
|
|
|
Give me a call with any questions, I have concrete coming around 8am for the basement but I won''t be doing the garage till flatwork down there is done. Phone #: ###-#### Inspection requested via web by Kellan Curtis,, heater is going on
|
BLD-Foundation | 12/3/2018 | 12/4/2018 | 12/4/2018 | P | NR |
Jim Storey
|
|
|
The garage foundation should be good to go. Give me a call if you have any questions. Phone #: ###-#### Inspection requested via web by Kellan Curtis need heat to remove snow in forms
|
BLD-Foundation | 11/18/2018 | 11/20/2018 | 11/20/2018 | A | PART |
Tony Young
|
|
|
Concrete is scheduled for 11am, give me a call with any questions Phone #: ###-#### Inspection requested via web by Kellan Curtis,, basement walls,, work in progress
|
BLD-Footing | 11/12/2018 | 11/13/2018 | 11/13/2018 | P | PART |
Tony Young
|
|
|
If you could give me a bit of a heads up before heading to the site that would be fantastic. I''ll be working on the other side of town but I''d love to shoot that way and walk things through with you. Phone #: ###-#### Inspection requested via web by Kellan Curtis,, basement and garage footings,, work in progress,, ok
|