Information based on query as of Saturday, May 18, 2024.
Permit Information
Permit NumberBLD19-00472
StatusFinaled
Name ROBERE KAZADI
Site Address 215 N BRUCE AVE
Project NameKline garage addition
Customer NumberDRH18-00502
ePlanReviewNo
Description
***PLAN MOD - BRAND NEW GARAGE BUILT ON CURRENT GARAGE LOCATION OK, NORTH WALL IS REQUIRED TO BE OF 1 HOUR CONSTRUCTION WITHOUT OPENINGS AND RATED SOFFITS OR BLOCKING FROM TOP PLATE TO UNDERSIDE OF ROOF SHEATHING TO OBTAIN A 1 HOUR RATED PROJECTION PER TABLE R302.1(1)** 09/16 MDH Permit for a new garage with mid height platform at back. 38'-6" x 20'-0" garage with P.E. roof trusses, slab on grade. Structural engineering provided. All work per plans, notations, attachments, engineering, local codes & ordinances. Separate electrical permit required. **MDH**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/3/20206/3/20206/3/2020ADONE
DetailsDave Hannah
All structural has been completed. A seperate electrical permit will be required when owner installes electrical wiring.
DOC - Permit Finaled  6/3/2020 DONE
DetailsDave Hannah
Electrical to be installed at a later date under seperate permit.
BLD-Conference5/15/20205/19/20205/19/2020ADONE
DetailsDave Hannah
Status? ext of project is done
BLD-Aging Inspection2/12/20202/12/20202/19/2020 PEND
DetailsDave Hannah
BLD-Aging Inspection2/11/20202/11/20202/19/2020 PEND
DetailsDave Hannah
BLD-Other10/24/201910/25/201910/25/2019APASS
DetailsMike Jordan
extiror drywall // robur Phone #: ###-####
BLD-Wall Bracing9/27/20199/30/20199/30/2019PPART
DetailsDave Hannah
Robere Phone #: ###-#### ext ok to cover but needs to install hold downs at garage door
BLD-Other9/16/20199/16/20199/16/2019PDONE
DetailsBob Archibald
Parcel tag has been removed, inspections and permits can now be obtained. A plan modification is required to address the fire rated requirements of the northern wall.
BLD-Other8/13/20198/13/20198/13/2019ADONE
DetailsBob Archibald
Reviewed site @ 11:15 am no work in progress. Roof sheathing had been completed since issuance of 1st citation.
BLD-Conference8/12/20198/12/20198/12/2019ADONE
DetailsBob Archibald
Issued citation to contractor, Robert Kazadi, Violation-BCC 9-1 Sec. R114.3
BLD-Other8/8/20198/8/20198/8/2019ADONE
DetailsBob Archibald
Tom with Code enforcement and I visited site to issue a citation for continuing to work after issuance of a SWO. No work in progress and no one on site. No citation issued.
BLD-Conference8/6/20198/6/20198/7/2019PDONE
DetailsDave Hannah
Issue SWO need plan modification and variance approval. swo issued and posted
BLD-Footing5/31/20196/3/20196/4/2019APASS
DetailsDave Hannah
Robere Phone #: ###-####