Permit Information
Permit NumberBLD19-01257
StatusFinaled
Name PORTER CHANDLER LLC
Site Address 4101 N CARTWRIGHT RD
Project NameHolman Residence
Customer Number 
ePlanReviewNo
Description
**HILLSIDE** **WUI FOOTHILLS ZONE A** **PRESCRIPTIVE ENERGY REQUIREMENTS** Permit for the construction of a new 4094 sq. ft., two story (first story 3059 sq. ft., second story 1035 sq. ft.) single family dwelling with 5 bedrooms, 3 bathrooms, approximately 619 sq. ft. of covered patio/porch and a 1834 sq. ft. attached garage per the approved plans and any notations. R-1B zoning and setbacks per planning. JJN
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/11/201912/12/201912/12/2019PPASS
DetailsTony Young
Loyd Phone #: ###-####
DOC - Permit Finaled12/12/201912/12/201912/12/2019PPASS
DetailsTony Young
c of o issued
BLD-Final12/11/201912/11/201912/11/2019PNR
DetailsTony Young
Loyd Phone #: ###-####,, needs egress,, handrail per code, fire caulking,, seal exterior doors as needed
BLD-Final12/10/201912/11/201912/11/2019ADEFR
DetailsTony Young
Loyd Phone #: ###-####.. defr to pm
BLD-Conference12/3/201912/3/201912/3/2019PPART
DetailsTony Young
Loyd Phone #: ###-####,, conf on final
BLD-Energy code compliance9/26/20199/27/20199/27/2019PPASS
DetailsTony Young
Loyd Phone #: ###-####
BLD-Framing/Rough-in9/27/20199/27/20199/27/2019APASS
DetailsTony Young
Loyd Phone #: ###-####
BLD-Energy code compliance9/27/20199/27/20199/27/2019APASS
DetailsTony Young
Loyd Phone #: ###-####
BLD-Framing/Rough-in9/18/20199/19/20199/19/2019APART
DetailsTony Young
call for access about 20 mins- Lloyd Phone #: ###-####// ok to insulate,, needs one more sprinkler inspection// minor frame corrections,, straps, blocking,, justify venting,, needs soffit protection on can lights
BLD-Wall Bracing8/7/20198/8/20198/8/2019APASS
DetailsTell Riley
LOYD Phone #: ###-####//shear nailing ok on exterior walls//crew is working on interior (garage) shear wall-check blocking at framing//
BLD-Foundation6/19/20196/20/20196/20/2019APASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing6/17/20196/18/20196/18/2019APASS
DetailsBrandon Shaw
Work in progress...