BLD-Final | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Tony Young
|
|
|
Todd Phone #: ###-####
|
DOC - Permit Finaled | 3/10/2020 | 3/10/2020 | 3/10/2020 | P | PASS |
Tony Young
|
|
|
c/n made ok,, guard rail meets code with solid// c of o issued
|
BLD-Final | 1/16/2020 | 1/17/2020 | 1/21/2020 | P | PEND |
Tony Young
|
|
|
Todd Phone #: ###-####
|
BLD-Blower Door Test Results | 1/16/2020 | 1/17/2020 | 1/17/2020 | P | DONE |
Tony Young
|
|
|
Todd Phone #: ###-####/// 4.3
|
BLD-Ceiling Grid Inspection | 1/16/2020 | 1/16/2020 | 1/16/2020 | P | NR |
Tony Young
|
|
|
Todd Phone #: ###-####,, needs trades,, fall protection on upstairs windows w/in 24", fire caulking,, cable guard rail engineering letter
|
BLD-Energy code compliance | 8/12/2019 | 8/12/2019 | 8/13/2019 | P | PASS |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Rutherford
|
BLD-Energy code compliance | 8/9/2019 | 8/12/2019 | 8/12/2019 | A | FAIL |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Rutherford// needs 6 sided coverage on insulation
|
BLD-Wall cover | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Rutherford,, insulation work in progress,, not ready
|
BLD-Framing/Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Rutherford,, ok to insulate,, some corrections needed,, listed out on truss engineering
|
BLD-Framing/Rough-in | 7/30/2019 | 7/31/2019 | 7/31/2019 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Rutherford. Needs mech. permit and rough in inspection.
|
BLD-Wall Bracing | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Rutherford
|
BLD-Footing | 5/6/2019 | 5/7/2019 | 5/7/2019 | P | PASS |
Jim Sly
|
|
|
We need inspection around 3:30-4, if possible. Phone #: ###-#### Inspection requested via web by Todd Rutherford
|