BLD-Blower Door Test Results | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | DONE |
Tell Riley
|
|
|
4.5 ACH 50
|
BLD-Final | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####
|
DOC - Permit Finaled | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 10/30/2019 | 10/30/2019 | 10/30/2019 | A | NR |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//need blower door completed//will call for re-inspection//
|
BLD-Energy code compliance | 8/29/2019 | 8/29/2019 | 8/29/2019 | P | PASS |
Tell Riley
|
|
|
to correct pending on last inspection//should be pass//
|
BLD-Other | 8/27/2019 | 8/27/2019 | 8/27/2019 | P | PASS |
Tell Riley
|
|
|
Fire rated soffits - Mark Phone #: ###-####//soffits per plans//
|
BLD-Energy code compliance | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | PEND |
Tell Riley
|
|
|
Mark Phone #: ###-####
|
BLD-Framing/Rough-in | 8/15/2019 | 8/15/2019 | 8/15/2019 | P | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####//corrections made//
|
BLD-Framing/Rough-in | 8/12/2019 | 8/13/2019 | 8/13/2019 | A | PASS |
Tell Riley
|
|
|
Phone #: ###-#### Inspection requested via web by Kelly Stover//add stud at bearing point for girder//need to call in soffit inspection when ready for rated soffits//ok to insulate only//
|
BLD-Wall Bracing | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####//add staples per plans at sole plate--working on it while onsite///
|
BLD-Foundation | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Tell Riley
|
|
|
|
BLD-Wall Bracing | 6/25/2019 | 6/25/2019 | 6/25/2019 | P | CANC |
Tell Riley
|
|
|
Mark Phone #: ###-####
|
BLD-Footing | 6/24/2019 | 6/24/2019 | 6/24/2019 | P | PASS |
Tell Riley
|
|
|
Mark Phone #: ###-####//setbacks ok per plans//rebar installed//footings setup per plans//
|