Information based on query as of Sunday, May 5, 2024.
Permit Information
Permit NumberBLD19-02360
StatusIssued
Name MAGALSKY MICHAEL
Site Address 2918 E EASTGATE DR
Project NameMagalsky Addition
Customer Number 
ePlanReviewNo
Description
HILLSIDE - Permit for a 1,045sq' addtion that expands the Kitchen & adds a Master Suite. Building 520sq' of new deck as well as a rebuild of the existing deck is part of this project. All work per plans, notations, attachments, engineering, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB** A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/6/20204/7/20204/7/2020APASS
DetailsBrandon Shaw
REMOTELEY INSP- Mike Phone #: ###-####
DOC - Permit Finaled4/7/20204/7/20204/7/2020PPASS
DetailsBrandon Shaw
BLD-Conference3/13/20203/13/20203/13/2020PDONE
DetailsBrandon Shaw
call for access- Michael Phone #: ###-####
DOC - Permit Finaled3/13/20203/13/20203/13/2020PPASS
DetailsBrandon Shaw
BLD-Energy code compliance2/13/20202/14/20202/14/2020APASS
DetailsBrandon Shaw
Jim Phone #: ###-####
BLD-Framing/Rough-in2/11/20202/12/20202/12/2020APASS
DetailsBrandon Shaw
Jim Phone #: ###-####
BLD-Framing/Rough-in1/21/20201/22/20201/22/2020PPART
DetailsBrandon Shaw
Kitchen area only...
BLD-Conference12/18/201912/19/201912/19/2019PDONE
DetailsBrandon Shaw
Mike Phone #: ###-####
BLD-Wall Bracing11/15/201911/18/201911/18/2019APASS
DetailsBrandon Shaw
shear // Dale Phone #: ###-####
BLD-Foundation10/25/201910/28/201910/28/2019ADONE
DetailsDave Hannah
as early as possible // Jim Phone #: ###-####
BLD-Foundation10/24/201910/25/201910/25/2019PDEFR
DetailsJim Storey
as early as possible // Jim Phone #: ###-####//out of time
BLD-Footing10/17/201910/18/201910/18/2019APASS
DetailsBrandon Shaw
Work in progress...