Permit Information
Permit NumberBLD19-02591
StatusFinaled
Name TRADEWINDS GENERAL CONTRACTING INC
Site Address 8639 W SLOAN ST
Project Name 
Customer NumberBLD19-02590
ePlanReviewNo
Description
**PRESCRIPTIVE ENERGY REQUIREMENTS** **TWO TOWNHOMES**ISSUE WITH BLD19-02590 Permit for the construction of a new 1365 sq. ft., 1 story Townhouse with 3 bedrooms, 2 bathrooms, approximately 30 sq. ft. of covered patio/porch and a 440 sq. ft. attached garage per the approved plans and any notations. R-2D zoning and setbacks per planning.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/9/201912/10/201912/10/2019PPASS
DetailsTony Young
Building final. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
DOC - Permit Finaled12/10/201912/10/201912/10/2019PPASS
DetailsTony Young
c of o issued
BLD-Final12/9/201912/9/201912/9/2019PPART
DetailsTony Young
Building final. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen// needs fire caulking
BLD-Energy code compliance12/4/201912/5/201912/5/2019ADONE
DetailsTony Young
Crawl space insulation inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
BLD-Other10/21/201910/22/201910/22/2019APASS
DetailsTony Young
Attic drywall. Phone #: ###-#### Inspection requested via web by Ed Kron
BLD-Wall cover10/21/201910/22/201910/22/2019APASS
DetailsTony Young
drywall inspection for seperation
BLD-Energy code compliance10/14/201910/14/201910/15/2019PDONE
DetailsTony Young
Exterior wall insulation inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
BLD-Energy code compliance10/14/201910/15/201910/15/2019APASS
DetailsTony Young
Exterior wall insulation inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen
BLD-Framing/Rough-in10/11/201910/14/201910/14/2019APART
DetailsTony Young
Framing and airseal inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen,, ok to insulate,, verify frame corrections at energy code
BLD-Framing/Rough-in10/11/201910/11/201910/11/2019PPART
DetailsTony Young
Framing and airseal inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen,, ok to insulate.. minor corrections on trusses
BLD-Wall cover9/24/20199/24/20199/24/2019PPASS
DetailsTony Young
Party wall truss sheetrock and fire blocking. Phone #: ###-#### Inspection requested via web by Nic Van Diepen
BLD-Framing/Rough-in9/24/20199/24/20199/24/2019PPART
DetailsTony Young
Shear re-inspection. Phone #: ###-#### Inspection requested via web by Nic Van Diepen.. ok after minor fixes
BLD-Framing/Rough-in9/20/20199/20/20199/20/2019PNR
DetailsTony Young
Shear inspection. Please call Nic a half hour before inspection. Thanks Phone #: ###-#### Inspection requested via web by Nic Van Diepen
BLD-Wall cover9/6/20199/6/20199/6/2019PPART
DetailsTony Young
main level firewall drywall ok to stand after finishing
BLD-Conference8/27/20198/28/20198/28/2019APASS
DetailsTony Young
Conference to determine inspection sequence for party walls between duplex units. Please call Nic a half hour before inspection. ###-#### Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen/// needs wall inspection before standing firewalls
BLD-Footing8/15/20198/15/20198/15/2019PPART
DetailsTony Young
Derik Phone #: ###-####
BLD-Footing8/14/20198/14/20198/15/2019PPART
DetailsTony Young
Derick Phone #: ###-####,, ok after fixing grade