BLD-Final | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | PASS |
Mike Jordan
|
|
|
This if for Final BLD Structural Inspection, the following inspections have previously been finaled for permanent occupancy (Electrical, FLS, FS, Mechanical, Plumbing) Structural is the only remaining for permanent occupancy. Phone #: ###-#### Inspection requested via web by David Hurley. Ok for perm occ.
|
BLD-Final | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PART |
Mike Jordan
|
|
|
Julian Phone #: ###-####. Ok to occupy cafeteria. Noted non functioning exit signs have been repaired. Fire extinguisher installed.
|
FIRE-Final Inspection | 3/17/2020 | 3/17/2020 | 3/17/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Julian Phone #: ###-####
|
BLD-Final | 3/16/2020 | 3/18/2020 | 3/17/2020 | A | CANC |
Dave Hannah
|
|
|
Julian Phone #: ###-####
|
BLD-Framing/Rough-in | 3/4/2020 | 3/6/2020 | 3/6/2020 | A | PASS |
Mike Jordan
|
|
|
Julian Phone #: ###-####. Interior steel stud framed walls for closet.
|
BLD-Framing/Rough-in | 2/21/2020 | 2/24/2020 | 2/24/2020 | A | PART |
Mike Jordan
|
|
|
Framing inspection Phone #: ###-#### Inspection requested via web by Julian Lopez. Interior steel stud framed walls for new storage and cafeteria areas. Pending electrical rough in inspection.
|