BLD-Final | 7/7/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Mike Jordan
|
|
|
Bubba *screened* Phone #: ###-####. Handrails for ramp have been installed. Ok for perm occ.
|
BLD-Final | 6/12/2020 | 6/15/2020 | 6/15/2020 | A | PART |
Mike Jordan
|
|
|
Bubba Phone #: ###-####. Ok for temp occ. Ramp from rear exit exceeds 5% slope and will require handrails.
|
BLD-Final | 6/11/2020 | 6/12/2020 | 6/12/2020 | P | PEND |
Mike Jordan
|
|
|
Bubba Phone #: ###-####. Need to verify slope of ramp on south side of building. Aslo needs public works sign off?
|
FIRE-Final Inspection | 6/11/2020 | 6/12/2020 | 6/12/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-####
|
BLD-Final | 6/9/2020 | 6/11/2020 | 6/11/2020 | P | CANC |
Mike Jordan
|
|
|
Bubba Phone #: ###-####. Cancelled by contractor via phone call.
|
FIRE-Final Inspection | 6/9/2020 | 6/11/2020 | 6/11/2020 | A | FAIL |
Troy Cobbley
|
|
|
Need to repair west exit discharge light and provide testing, as discussed, for the duct smoke detectors.
Bubba Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Brandon Shaw
|
|
|
screened // Bubba Phone #: ###-####
|
BLD-Framing/Rough-in | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | PASS |
Mike Jordan
|
|
|
Carven **cleared** Phone #: ###-####. Interior steel stud framed walls ok. hardlids and soffits ok pending MEP's rough in inspections.
|