Information based on query as of Monday, May 20, 2024.
Permit Information
Permit NumberBLD19-04921
StatusIssued
Name STRAIGHT LINE BUILDING SOLUTIONS LL
Site Address 2623 S FRY ST
Project NameWest Airport Ind Park - Bldg C
Customer Number 
ePlanReviewYes
Description
(WEST AIRPORT INDUSTRIAL PARK – BLDG C – 2ND BUILDING FROM THE EAST – WAREHOUSE SHELL) (DRH18-00264 and DRH18-00332) The fire sprinkler system is used for building area increase and for fire area. To construct a new 37,182 square foot warehouse shell building (380’ x 100’ exterior dimensions). Work is to include concrete footings, concrete tilt-up wall panels, concrete floor sabs on grade, steel columns with steel baseplates and anchors, steel roof girder trusses, steel roof trusses, metal roof deck, insulation on top of the roof deck, single-ply TPO roof membrane, domed plastic skylights, wall insulation, exterior overhead doors, exterior storefront windows, exterior doors, exterior steel stairways with steel landings, two trash enclosures with steel gates, steel awnings with steel support tie-back rods, a keystone block retaining wall at the sloped grade, a 40 foot wide concrete apron at the loading dock area, and a 1-hr fire sprinkler riser room with an exterior door. Special inspection is required for soils, concrete, steel (including welding and bolting), and anchors post-installed in hardened concrete. Future roof top HVAC units weighing 750 pounds each were anticipated. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. This permit is not intended to establish a Certificate of Occupancy for any portion of this building. Separate permits are required to establish occupancy. A safe dispersal area is required on the West and on the East side of Building B because, due to excessive slopes, there will not be an accessible means of egress provided to the public way. A service sink and perhaps drinking fountains and two toilet rooms for each tenant space will be required under future tenant improvement permits. **MDH**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Concrete8/11/20208/11/20208/12/2020PDEFR
DetailsMike Jordan
rebar Phone #: ###-#### Inspection requested via web by Todd Landvatter. Ok pending special inspection.
BLD-Concrete8/10/20208/10/20208/10/2020PPASS
DetailsMike Jordan
rebar for pour back strip Phone #: ###-#### Inspection requested via web by Todd Landvatter. Interior slab on grade for pour back strip, east half.
BLD-Concrete7/10/20207/13/20207/13/2020APART
DetailsMike Jordan
trash encloser walls Phone #: ###-#### Inspection requested via web by Todd Landvatter
BLD-Footing7/7/20207/8/20207/8/2020APASS
DetailsMike Jordan
concrete at 11am Phone #: ###-#### Inspection requested via web by Todd Landvatter. Footings for trash enclosure.
BLD-Concrete6/15/20206/16/20206/16/2020ADEFR
DetailsMike Jordan
steel for wall panels Phone #: ###-#### Inspection requested via web by Todd Landvatter. Ok pending special inspection.
BLD-Footing5/22/20205/26/20205/26/2020APART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. East footing. Needs to provide 3 inch clearance from ground in several areas. Ok to place concrete pending special inspection.
BLD-Footing5/15/20205/18/20205/18/2020PPART
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. East exterior footing and northeast and southeast fotting to stepdown. work in progress. Ok to place pending special inspection.
BLD-Concrete4/23/20204/24/20204/24/2020APART
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by Todd Landvatter pannels pending si report.
BLD-Foundation3/26/20203/27/20203/27/2020APASS
DetailsMike Jordan
steel. any time 10:00 on. Phone #: ###-#### Inspection requested via web by Todd Landvatter. Interior slab on grade ok.
BLD-Foundation3/26/20203/27/20203/26/2020PCANC
DetailsMike Jordan
Phone #: ###-#### >> Inspection requested via web by Todd Landvatter Inspection cancelled from web by: Todd Landvatter
BLD-Footing3/18/20203/19/20203/19/2020PPASS
DetailsMike Jordan
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Interior column pad footings ok.